Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Children Display

Table of Contents


Release Name

Current Phase

Release Date

Next Phase

TimelineRSAC requirements at release start
E releasePlanningDec 2021Requirements Definition
link
D ReleaseDevelopment

02 Jul  

Test and Publishsee belowlink
CherryCurrent Release

 

EOLtimelinelink
BronzeEOL

  

EOLtimelinelink
AmberEOL

 

EOLnot available

Status Definitions:


Status

Meaning

1PlanningPre-M0.  The release name has been chosen and tentative milestone dates have been determined.
2Requirements DefinitionBetween M0 and M1.  Timeline is approved.  Epics and User Stories are labeled with the release names and entered into jira.
3DevelopmentAfter M1 and before release.  Code development for sprints updated in jira.
4Current ReleaseThe approved output of the release process which interested end users should be deploying. This release will be maintained until it is replaced by the next release.
5End of Life (EOL)Release is complete.