Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

This page contains a table with criteria and some notes on what the PTL and commiters need to check as part of release preparation. It is influenced by CII badging criteria CII status: near-RT RIC.

Release Criteria (RC) headlineCriteria details/references
RC-1 PTL: Check that we have a release summary. Committers: check that release notes are updated in RST file in gerrit.Did every component update their rst release notes & did PTL summarized those on one wiki page? See CII criteria [release_notes]
in
RC-2: Check that we have all fixed security bugs listed in release notes

For own source-code bugs this can be handled manually as part of release checklist (If JIRA based security bug has been created)

But for containers we should find a technical solution (automated) involving some tool e.g. docker image scanning tool (LFN provided preferred). See also CII criterium [release_notes_vulns]

in 

RC-3: Save one-time snapshots of some reportsStore a snapshot copy of the reports of the following three criteria into wiki page: (1) The project MUST acknowledge a majority of bug reports submitted in the last 2-12 months (inclusive); the response need not include a fix. and (2) The project SHOULD respond to a majority (>50%) of enhancement requests in the last 2-12 months (inclusive). (3) The project's initial response time for any vulnerability report received in the last 6 months MUST be less than or equal to 14 days.