Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  1. Bronze status:
    1. TS use case xApps (TS, QP-D,QP) ready, tested, and released, KPIMON delayed until maintenance release due to legal review (+ testing required)
    2. HW demo and MC xApp also ready, tested and released
  2.  Cherry progress:
    1. Planning underway for the extension to the traffic steering use case, WG-3 spec will likely arrive late but we will try to accommodate it if possible
    2. QP-D: raises and cancels alarms (SDL availability) - first RIC component to raise an alarm
    3. In progress: all open source xApps using RIC SDK APIs for O1-PM/FM (alarms/metrics), O1-CM (configuration) and A1-P (policy intent).

2020-07-07

  1. Bronze and Bronze maintenance status update.
    1. Bronze done with 5 xApps
    2. Waiting for Samsung KPIMON and Viavi simulator output for the maintenance release.
  2. Cherry progress.
  3. How to contribute:
    1. Help with an existing xApp (Find an unassigned user story here https://jira.o-ran-sc.org/projects/RICAPP/ and contact me)
    2. Suggest a new xApp idea.