Note: Recording of meetings available here: Project meetings

2022-03-01:

Status:

  • Updates:  
    • SDK repos: Facebook is waiting for a resolution on the CLA issue before submitting code, C++ repo approved but needs to be created using self-service methods  - CLA issue is still not resolved. Need to figure out the next steps. committer is not available.  - No reply from Facebook
    • Vmware working on the repo creation. Aditya is working on the info.yaml file. (Repo for cpp sdk) - CLA issue
    • REST API in progress for RIC subscription in Bouncer xApp and CPP framework - F release
      • REST API based Implemenation. - In-progress
    • Test Automation - Subscription Deletion - Completed - code check-in - In progress
      • A1 Mediator E2E test (Tested with HW, Need to check with Bouncer xApp). - Already covered in RICP. - Manual Testing completed. Automation in progress  
    • HW (Python) - Subscription - Target to complete F-Release - Need to check with Naman. (Subscription)
    • RC xApp -  
      • Latest E2AP version (2.0) -  Upgrade will be done.   RC xApp will support new version. Dependency on RICP for E2AP 2.0. - In progress. Jenkins job is fixed. 
    • LP xApp - existing KPM metrics - checking with china team to use metrics. but no conclusion yet. No Updates
    • AI - Sunil - OTF testing for xApps - Had internal discussion with the team. No conclusion yet.
    • TS - Some parameters need to be checked from where to grab these parameters from AD and QP messages  - Checked with Deepanshu
      • Alexandre - Any updates?
    • KPIMON xApp.  
      • Mail sent to wansu.yoo@samsung.com for the ownership. - No Response. 
      • HCL will work on this xApp -  New repo needs to be created. Will get teh TOC approval for the new repo.
    • New proposal
      • Network Slice AD management - HCL & Alexandre -

2022-02-15:

Status:

  • Updates:  
    • SDK repos: Facebook is waiting for a resolution on the CLA issue before submitting code, C++ repo approved but needs to be created using self-service methods  - CLA issue is still not resolved. Need to figure out the next steps. committer is not available.  - No reply from Facebook
    • Vmware working on the repo creation. Aditya is working on the info.yaml file. (Repo for cpp sdk) - CLA issue
    • REST API in progress for RIC subscription in Bouncer xApp and CPP framework - F release
      • REST API based Implemenation. - In-progress
    • Test Automation - Subscription Deletion - In progress, A1 Mediator E2E test (Tested with HW, Need to check with Bouncer xApp). - Already covered in RICP.  
    • HW (Python) - Subscription - Target to complete F-Release - Need to check with Naman. (Subscription)
    • HW (GO) - New release is pushed for E- Maintenance Release.  - Updated, new image is available in Nexus repo. - need to update the release table in wiki page. - Updated. Closed.
    •  RC xApp -  
      • Latest E2AP version (2.0) -  Upgrade will be done.   RC xApp will support new version. Dependency on RICP for E2AP 2.0. - In progress. Jenkins job is fixed. 
    • LP xApp - existing KPM metrics - checking with china team to use metrics. but no conclusion yet. No Updates
    • AI - Sunil - OTF testing for xApps - Need to check with HCL team and update in next meeting.
    • TS - Some parameters need to be checked from where to grab these parameters from AD and QP messages  - Need to check with Deepanshu.
    • KPIMON xApp.  
    • New proposal
      • Network Slice AD management - HCL & Alexandre - No updates.

...