2022-03-29:

Status:

  • Updates:  
    • SDK repos: Facebook is waiting for a resolution on the CLA issue before submitting code, C++ repo approved but needs to be created using self-service methods  - CLA issue is still not resolved. Need to figure out the next steps. committer is not available.  - No reply from Facebook - CLA issue is not resolved. Files are available for Python SDK. Files with BSD license. It is ok to have the BSD files.  Any Updates? 
    • Vmware working on the repo creation. Aditya is working on the info.yaml file. (Repo for cpp sdk) - CLA issue - Same status - They will work in April
    • REST API in progress for RIC subscription in Bouncer xApp and CPP framework - F release
      • REST API based Implemenation. - Done
        • Checking on the xAPP framework.

...

        •   - Working on
    • HW (Python) - Subscription - Target to complete F-Release - Need to check with Naman. (Subscription) - No updates
    • HW(GO) - In maintenance release.
    • RC xApp -  
      • Latest E2AP version (2.0) -  Upgrade will be done.   RC xApp will support new version. Dependency on RICP for E2AP 2.0. - In progress. Jenkins job is fixed. 
      • No updates in the current releases. Need to create the JIRA ticket to check the status 
      • E2SM RC 1.0.1 and E2AP 2.0 - compiled and Testing. 
      • ToDo - Raise Jira tickets for the RC-xApp
    • LP xApp - existing KPM metrics - checking with china team to use metrics. but no conclusion yet. No Updates (James)
    • AI - Sunil - OTF testing for xApps - Had internal discussion with the team. No conclusion yet. -

...

    •   session planed next week on OTF.
    • TS - Some parameters need to be checked from where to grab these parameters from AD and QP messages  - Checked with Deepanshu
      • Sangeetha working on Integration setup. E2AP Version 1.1 support.
      • we will check with VIAVI if they support E2.o by the end of this release.   
      • Alexandre - Any updates? E2 Config info in E2 Setup - RNIB - Information population. - Getting RAW data. Need to decode the data.
      • Subhash - cli tool for RNIB can be used to populate the info. Need to check
    • KPIMON xApp.  
      • HCL will work on this xApp -  New repo needs to be created. Will get the TOC approval for the new repo. - Approval done
        • Repo Creation - Need to check with Mavenir and VMWare mails. 
          • HCL will look into the wiki. 
          • Samsung will be added as a committer. Subhash will provide the committers list.

...

    • Subscription issue with the python framework - Need to check with Amit. (Rest based implementation)
    • Code coverage on RICAPP. - Discussion

2022-03-15:

Status:

  • Updates:  
    • SDK repos: Facebook is waiting for a resolution on the CLA issue before submitting code, C++ repo approved but needs to be created using self-service methods  - CLA issue is still not resolved. Need to figure out the next steps. committer is not available.  - No reply from Facebook - CLA issue is not resolved. Files are available for Python SDK. Files with BSD license. It is ok to have the BSD files.  Matti will reply to this.  
    • Vmware working on the repo creation. Aditya is working on the info.yaml file. (Repo for cpp sdk) - CLA issue - Same status.
      • Same status.
    • REST API in progress for RIC subscription in Bouncer xApp and CPP framework - F release
      • REST API based Implemenation. - Done
        • Checking on the xAPP framework
    • Test Automation - Subscription Deletion - Completed - code check-in - In progress
      • A1 Mediator E2E test (Tested with HW, Need to check with Bouncer xApp). - Already covered in RICP. - Manual Testing completed. Automation Completed - Code check-in in progress
    • HW (Python) - Subscription - Target to complete F-Release - Need to check with Naman. (Subscription) - No updates
    • RC xApp -  
      • Latest E2AP version (2.0) -  Upgrade will be done.   RC xApp will support new version. Dependency on RICP for E2AP 2.0. - In progress. Jenkins job is fixed. 
      • No updates in the current releases. Need to create the JIRA ticket to check the status 
    • LP xApp - existing KPM metrics - checking with china team to use metrics. but no conclusion yet. No Updates (James)
    • AI - Sunil - OTF testing for xApps - Had internal discussion with the team. No conclusion yet. - No updates
    • TS - Some parameters need to be checked from where to grab these parameters from AD and QP messages  - Checked with Deepanshu
      • Sangeetha working on Integration setup. E2AP Version 1.1 support.
      • we will check with VIAVI if they support E2.o by the end of this release.   
      • Alexandre - Any updates? E2 Config info in E2 Setup - RNIB - Information population.
      • Subhash - cli tool for RNIB can be used to populate the info. Need to check
    • KPIMON xApp.  
      • HCL will work on this xApp -  New repo needs to be created. Will get the TOC approval for the new repo. - Approval done
        • Repo Creation - Need to check with Mavenir and VMWare mails. 
          • HCL will look into the wiki. 
          • Samsung will be added as a committer. Subhash will provide the committers list
    • Subscription issue with the python framework - Need to check with Amit.
    • New proposal
      • Network Slice AD - HCL & Alexandre

...