Update from WG6 Test Group

For Nov Train:

  • Conformance Test spec approved.
  • IOT spec update, for Friday review.

For O-Cloud Certification:

  • Test Req Status CR will be started in early Dec which is planned for Jan 2024 WG6 approval.
  • IOT spec is not plan required for certification since it’s for badging, but currently no badging plan.
  • Docomo will share the draft CR before send to TIFG review.
  • Notification API test diagram will be synced up with CAD, after the CR to CAD for March Train.

Others:

  • End of Dec meeting planned to be cancelled (TBC).