O-DU-High Status Report 15 Oct 2019
F1 Interface APIs: Work In Progress
- Initial configuration messages between CU and DU being developed. List of APIs being targeted currently is:
- F1 SETUP REQUEST
- F1 SETUP RESPONSE
- GNB-DU CONFIGURATION UPDATE
- GNB-DU CONFIGURATION UPDATE ACKNOWLEDGE
- Testing for these messages is work in progress.
- Fixed few issues with ASN generated code.
O-DU-OAM-Agent – Work In Progress
- Initial bring up of the system and layer configuration.
- Testing is work in progress
MAC-PHY (FAPI) Interface
- Discussions with the O-DU Low team is in progress.
- Test code development is WIP for initial PHY configuration messages.
- Testing is work in progress.
Opens
- Release-B Planning
- Interfaces development O1, E2 planning
- ODU-Low FAPI Integration plan, dependency on L1 FAPI APIs
- Scheduler development plan
- Testing infrastructure (softwares) - UE SIM, OCU and Core
O-DU-High Status Report 11 Sep 2019
F1 Interface APIs: Work In Progress
- ASN 1 being used from https://gerrit.o-ran-sc.org/r/com/asn1c.git
- Initial configuration messages between CU and DU being developed. List of APIs being targeted currently is:
- F1 SETUP REQUEST
- F1 SETUP RESPONSE
- GNB-DU CONFIGURATION UPDATE
- GNB-DU CONFIGURATION UPDATE ACKNOWLEDGE
O-DU-OAM-Agent – Work In Progress
- Initial bring up of the system and layer configuration.
MAC-PHY (FAPI) Interface
- Discussions with the O-DU Low team is in progress.
- Test code development is WIP for initial PHY configuration messages.
O-DU-High Status Report 11 Sep 2019
F1 Interface APIs: Work In Progress
- ASN 1 being used from https://gerrit.o-ran-sc.org/r/com/asn1c.git
- Initial configuration messages between CU and DU being developed. List of APIs being targeted currently is:
- F1 SETUP REQUEST
- F1 SETUP RESPONSE
- GNB-DU CONFIGURATION UPDATE
- GNB-DU CONFIGURATION UPDATE ACKNOWLEDGE
O-DU-OAM-Agent – Work In Progress
- Initial bring up of the system and layer configuration.
MAC-PHY (FAPI) Interface
- Discussions with the O-DU Low team is in progress.
- Test code development is WIP for initial PHY configuration messages.