  1. Review and agree to minutes of previous meetings
  2. check RIC-95 status
  3. postponed items (out of Bronze): RIC-76 (subscription manager)

2020-04-28

Recording: TODO near_rt_ric_platform_project_meeting_2020_04_28.mp4

  1. Review and agree to minutes of previous meetings
  2. FYI RICP (combined with RICAPP) demos are every third week: Sprint demos
  3. Status of
    1. RIC-95 (design approved by tel aviv teams // implementation should be ready // problem with testing as no access to simulator) Tel Aviv cannot test with proprietary simulator as no time. This might delay RIC-95 further. Harry cannot help as on leave. Ron might get simulator ready within two weeks, but there is some risk that service query is not working yet in simulator. Arunkumar could take a look at the service query support in simulator during next week once RIC-95 is ready. If we make good progress, we could still push this into maintenance release (after TOC approval).
    2. RIC-203 no progress. design not clear yet. Drop this from Bronze (not try to push it into maintenance release)
  4. postponed DB items EPICS: (not even started):  RIC-123, RIC-107, RIC-118 and RIC-119 as well as user story: RIC-104 to post-Bronze-R4
  5. 2020-04-28: epics still open team 1: 17, team 2: 5, team 3: 3, team 4: 8 : team 5: 10, team 6: 2, team 7: 2. sum = 47 still open
  6. FYI: Tommy Carpenter has left the project. Committer upgrade needed. A1, xapp-frame-py → Chris Lott. RMR python version is in xapp-frame-py. RMR also replace tommy with Chris (even if no RMR python work a<nymore), Rpanta also remove from RMR repo. The repo "utils" we should remove. Add Chris now. Remove Tommy after Bronze. Thoralf to initiate this change.

...