2020-09-29
Recording: TODO
- reminder on next demo: 2020-10-15 Cherry R6.2 . Pls. add anything you want to demo there.
- RIC-360 any progress. Discussion with Nune and Nithin kept?
- deployment script changes (Abdulwahid) related to helm3. Discussed with Felix (onboarder (felix) changes still needed).
- appmgr changes no discussion → Nune
- Thoralf to invite meeting with Alok + Sri + ramesh (still this weeks)
- RIC-509
- subitems being worked on by LF next.
- RIC-109: since Jussi on holiday pls. involve Timo T (another committer for dbaas)
- RIC-249 (of RIC-95) currently blocked by XML-to-PER conversion of RIC_SERVICE_UPDATE_ACK.
- Thoralf still to test the 1-week old code that Rahul wrote (RIC-248)
- This now hangs with Adi.
- Also another issue is how an empty RIC Service Query/update would look like. ASN.1 is also a bit unclear.
- RIC-203 is still in team S1 or currently nobody planning to work on this?
- Rahul might be able to work on this, but earliest decision on this in next meeting.
- some items postponed from Cherry to Dawn: RIC-202 (TODO-check) - the alarm for E2 connection lo0ss not coming in Cherry. RIC-139, RIC-421likely post-cherry.
- Subhash xApp demo can be in platform code. Subhash would like to discuss this.
- RICAPP agenda: RICAPP Meetings.
...