    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for I release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. input for release candidates: left overs and generally open items, RSAC
    3. Sprint dates
      1. Sprint I release dev sprint 1: Aug-21 to Sep-10
      2. Sprint I release dev sprint 2: Sep-11 to Oct-1
      3. Sprint I release dev sprint 3: Oct-2 to Oct-22
      4. Sprint I release dev sprint 4: Oct-23 to Nov-12 (last planned development sprint)
      5. Sprint I release dev sprint 5: Nov-13 to Dec-3 (only for unplanned last-minute development items)
    4. Plan (v03 as of 2023-08-18):
      1. I release plan moved to I release page.

      Completion status


  1. RICAPP agenda: RICAPP Meetings.

...