Note that the links to the recordings before 2021-03-16 where mp4 files. They broke when copying the text into this archive page. You can still find them as attachments to the original meetings page Project meetings -> click on the three dots in the upper right corner and select “Attachments” from the menu.

2023-10-24

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-09-26
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/alarm-go/+/11149 OK, go version update only
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/lib/rmr/+/11234 OK, test case added for IPv6 tests
      3. https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/11324 OK, test case updated
      4. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/11733 OK, generated code from API
      5. https://gerrit.o-ran-sc.org/r/c/ric-plt/submgr/+/11681 ok, (not yet merged)
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-05-23:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1019 xapp-frame - incorrect removal of transmitted rmr message in unsuccessful case (Juha) → DONE
    2. RIC-1017 xapp-frame -  xapp-frame may not be able to successfully subscribe to messages
    3. RIC-1016 e2t sctp_params structure may not be initialized properly

    4. RIC-1015 e2t too High default message size.

    5. RIC-1014 e2t potential race condition in the `listener` function due to multiple `listener` threads.

    6. RIC-1013 e2t e2term pod does not become ready. Possible stack/heap corruption 

    7. RIC-1012 RMR not working in A1 mediator → DONE (Thoralf also released fixed image in ric-dep recipe of h-release)
    8. RIC-1009 E2Mgr API can be improperly invoked → convert to bigger Epic?
    9. RIC-1002 (Nokia fixes) Abnormal signaling process cause E2Term crash (this could be a security issue)
    10. RIC-1001 RMR service should verify route tables - Alexandre will take a look
    11. RIC-991 RMR related (not a duplicate) - Alexandre will take a look
    12. RIC-989 RMR (minor) security issue - Alexandre will take a look
    13. RIC-972 (Naman) URL for A1 mediator to align with spec.
    14. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    15. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    16. RIC-915 dms_cli for installing xapp not working (raised by James)
    17. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    18. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    19. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    20. RIC-894 long idle period (days) causes RMR connection breaks
    21. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    22. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    23. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    24. RIC-837 RMR is not forwarding messages from E2T to E2M
    25. RIC-835 → 2021-12-07 no news from Viktor
    26. fixed: RIC-1019, RIC-1012
  4. James: updates?
    1. 2023-09-12: requested from PTLs pair-wise testing. From Near-RT RIC point of view we hope for the non-RT RIC project to initiate testing with A1 mediator standalone version.
    2. 2023-09-26: This was presented in TOC (See link). Cases relevant for near-RT RIC:
      1. ODU-high and near-RT RIC (currently using stub).
      2. near-RT RIC and xApp (KPIMON/bouncer or maybe adding CCC xApp)
      3. near-RT RIC and non-RT RIC (A1) - next step on non-RT RIC side (A1 standalone mediator provided)
      4. James will check with Sunil on issues he has with the test cases
      5. ArgoCD used by Taiwan lab in some ONAP SMO  case and the engineers there where wondering if something similar could be done with OSC.
    3. 2023-10-24
      1. updates from O-RAN f-2-f:
        1. nephio and OAI discussion: Nephio team would like to add RAN components (OAI, OSC, and parts of the OSC SMO (via Seshu) into R2 (~Feb2024)
        2. OAI had three demos. One of them is about improving QoE with H release of near-RT RIC using some code copied from KPM and hello world xApps.
          1. see demo "oai-osc-ric-demo.mp4" in link and the demo session recording on the O-RAN web site (thoralf-todo)
          2. more discussion coming at the joint OSC/OAI workshop in Boston
        3. session on SCCL did make some progress in that WG10/WG6 understanding improved. Additional discussion scheduled under O-RAN umbrella for Oct-31.
      2. OSFG discussed on the super wireless footprint (matrial available at O-RAN OSFG)
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22, 2023-09-26 : could not participate
  6. Sunil updates (subteam-h)?
    1. 2023-09-12: can give update next time. Maybe 2 or 3 items to work on.
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-08-29: no news, other than Naman working on the operator implementation.
    2. 2023-09-12:
      1. We had a meeting with John and Denis on non-rt RIC compatibility. Agreed in fixes for URL and policystatusobject type from integer→string (as per standard) → Naman.
      2. Thoralf to figure out a way to start A1 mediator standalone for CI testing
        1. Thoralf sent instructions to John → DONE
      3. current implementation of /data-delivery URL in A1 - need to check if >1 consumer of EI data (sent by non-RT RIC) works on our side.
      4. Naman also works on the operator implementation
    3. 2023-09-26:
      1. kubernetes operator new repo needed or not?
        1. xapp deployment → appmgr or ricdms
        2. ric platform → ric-dep (still work in progress) - check if operator can use helm chart defined by Abhijit.
      2. What happened to kserve adapter? → Subhash can check.
  8. Abhijit updates (subteam-ag) ?
    1. 2023-08-22: next release item discussed and RIC-979
    2. 2023-08-29:
      1. created RIC-1004 for release I item.
      2. still working on RIC minimal implementation (demo coming once ready, might take still weeks)
        1. once it's somewhat usable, pls. place into subdirectory under ric-plt/ric-dep
    3. 2023-09-12:
      1. changes related to registration API needed in xapp-frame (problem still to be thought of)
      2. something not working in github: IT-25974 - again related to github replication.
    4. 2023-09-26
      1. Abhijit presented his work on a single near RT RIC helm chart and bringing up the platform on minikube on Ubuntu 22.04. We decided to proceed with this.
      2. github action problem with master vs g release for replication → ticket → DONE
      3. Abhijit wanted to provide a video for new way of ric deployment (2023-10-24: did not find time to finally do this)
    5. 2023-10-24:
      1. Abhijit and James release new base image: docker pull nexus3.o-ran-sc.org:10002/o-ran-sc/bldr-ubuntu22-c-go:0.1.0 → still to be made 1.0.0
      2. no progress in review on the plain helm chart based deployment in https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/11743 
      3. Abhjit raise RIC-1013 ... RIC-1017 for issues he has discovered. Thoralf to find someone to work on it.
  9. Cap Gemini updates (subteam-cg)? 
    1. Conflict detection and management. Presentation by Gunja on Sep-12 link-to-slideset
      1. Ashish S. (CapGemini) presented this.
      2. Thoralf will initiate a new repo for this: ric-plt/conflictmgr
        1. this might become an optional or mandatory (but default-disabled) component of thr near-rt ric platform.
        2. todo-cap-gemini: align usage of UE ID with wg3 discussion on this.
        3. additional latency comes only from guidance request
        4. xapp-framework could be extended to automatically do E2 guidance requests
    2. 2023-09-26:
      1. first step of new repo created, but still issues with initial files in repo. Thoralf raised request to LF: https://jira.linuxfoundation.org/plugins/servlet/desk/portal/2/IT-26015 
    3. 2023-10-10:
      1. conflictmgr repo is now ready for commits: https://gerrit.o-ran-sc.org/r/admin/repos/ric-plt/conflictmgr,general
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. 2023-08-29: ready for merging once the CI problem (gofmt) is fixed. Can be merged together with a change in the helm chart (ric-dep). Default behavior is "strict order" (as currently). But config value can change to "any order".
  11. Dhiraj (subteam-r)
    1. 2023-08-22:
      1. checking compliance/license issues
      2. How are policy types created? xApps register by policy type and understands the schema that is bound to it. Non-RT RIC should create policies using the same schema (there's a GUI for this on non-RT RIC side).
    2. 2023-08-29:
      1. got clarity on license issues and now waiting for internal approval before publishing ipv6 releated changes
  12. Alexandre (subteam-utfpr)
    1. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
    2. 2023-09-26: subscription message issue with encoding E2SM parts. A. will send e-mail to Thoralf
  13. Nokia (subteam-n)
    1. ...
  14. I release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for I release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. input for release candidates: left overs and generally open items, RSAC
    3. Sprint dates
      1. Sprint I release dev sprint 1: Aug-21 to Sep-10
      2. Sprint I release dev sprint 2: Sep-11 to Oct-1
      3. Sprint I release dev sprint 3: Oct-2 to Oct-22
      4. Sprint I release dev sprint 4: Oct-23 to Nov-12 (last planned development sprint)
      5. Sprint I release dev sprint 5: Nov-13 to Dec-3 (only for unplanned last-minute development items)
    4. Plan (v03 as of 2023-08-18):
      1. I release plan moved to I release page.
  1. RICAPP agenda: RICAPP Meetings.


2023-10-10

no meeting as neither Thoralf nor Sunil were available to host the call

2023-09-26

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-09-26
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/alarm-go/+/11149 OK, go version update only
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/lib/rmr/+/11234 OK, test case added for IPv6 tests
      3. https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/11324 PK, test case updated
      4. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/11733 OK, generated code from API
      5. https://gerrit.o-ran-sc.org/r/c/ric-plt/submgr/+/11681 ok, (not yet merged)
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-05-23:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1011 (Nokia fixes) E2 error with cause duplicate-error for all subscriptions requests after resource-limit failure - FIXED
    2. RIC-1009 E2Mgr API can be improperly invoked → convert to bigger Epic?
    3. RIC-1002 (Nokia fixes) Abnormal signaling process cause E2Term crash (this could be a security issue)
    4. RIC-1001 RMR service should verify route tables - Alexandre will take a look
    5. RIC-991 RMR related (not a duplicate) - Alexandre will take a look
    6. RIC-989 RMR (minor) security issue - Alexandre will take a look
    7. RIC-979 (Abhijit will close this one) Decode Error with e2sim on e2term Pod - 2023-08-22: Abhijit still looking into this, but with latest Ubuntu packages this seems not to cause the problem anymore.
    8. RIC-972 (Naman) URL for A1 mediator to align with spec.
    9. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    10. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    11. RIC-915 dms_cli for installing xapp not working (raised by James)
    12. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    13. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    14. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    15. RIC-894 long idle period (days) causes RMR connection breaks
    16. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    17. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    18. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    19. RIC-837 RMR is not forwarding messages from E2T to E2M
    20. RIC-835 → 2021-12-07 no news from Viktor
    21. fixed: RIC-1011, RIC-979
  4. James: updates?
    1. 2023-08-01:
      1. O2 integration with OSC RIC is still pending with WR.
      2. OAI was discussed in last week's TOC, and it seems OAI license is not blocker for using OAI in OSC-labs.
    2. 2023-08-22:
      1. Can we do pair-wise testing, e.g., between (1) xapp and RIC, (2) non-RT RIC ↔ near-RT RIC testing (only A1) ?
        1. E.g., KPIMON or bouncer xApp could be used. Sunil might be able to help.
        2. e.g., existing discussion with John
    3. 2023-08-29: no news
    4. 2023-09-12: requested from PTLs pair-wise testing. From Near-RT RIC point of view we hope for the non-RT RIC project to initiate testing with A1 mediator standalone version.
    5. 2023-09-26: This was presented in TOC (See link). Cases relevant for near-RT RIC:
      1. ODU-high and near-RT RIC (currently using stub).
      2. near-RT RIC and xApp (KPIMON/bouncer or maybe adding CCC xApp)
      3. near-RT RIC and non-RT RIC (A1) - next step on non-RT RIC side (A1 standalone mediator provided)
      4. James will check with Sunil on issues he has with the test cases
      5. ArgoCD used by Taiwan lab in some ONAP SMO  case and the engineers there where wondering if something similar coudl be done with OSC.
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22, 2023-09-26 : could not participate
  6. Sunil updates (subteam-h)?
    1. 2023-07-18, 2023-08-01, 2023-08-22, 2023-08-29: no news
    2. 2023-09-12: can give update next time. Maybe 2 or 3 items to work on.
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-08-01:
      1. E2AP v3.0 → we took a look at what changes are coming 
      2. A1 enhancements
      3. considering upgrade of ubuntu and k8s
      4. deploying RIC and xapps using k8S operator I_Release_Proposal_Samsung_Naman.pptx
      5. DMS delete PI
      6. E2 reset from ric to e2 node
    2. 2023-08-22: we discussed Jira item priority.
    3. 2023-08-29: no news, other than Naman working on the operator implementation.
    4. 2023-09-12:
      1. We had a meeting with John and Denis on non-rt RIC compatibility. Agreed in fixes for URL and policystatusobject type from integer→string (as per standard) → Naman.
      2. Thoralf to figure out a way to start A1 mediator standalone for CI testing
        1. Thoralf sent instructions to John → DONE
      3. current implementation of /data-delivery URL in A1 - need to check if >1 consumer of EI data (sent by non-RT RIC) works on our side.
      4. Naman also works on the operator implementation
    5. 2023-09-26:
      1. kubernetes operator new repo needed or not?
        1. xapp deployment → appmgr or ricdms
        2. ric platform → ric-dep (still work in progress) - check if operator can use helm chart defined by Abhijit.
      2. What happened to kserve adapter? → Subhash can check.
  8. Abhijit updates (subteam-ag) ?
    1. 2023-05-23
        1. hw-rust xapp using xapp descriptor (config.json) works, but still fixing lifeness and readiness probe
        2. testing of subscriptions using hw-rust (facing the E2T problem)
    2. 2023-07-18: no news
    3. 2023-08-01: got logs from Subhash. Now ran into issues with Dockerfile in E2T (gcc related differences between ubuntu 20 and 22)
    4. 2023-08-22: next release item discussed and RIC-979
    5. 2023-08-29:
      1. created RIC-1004 for release I item.
      2. still working on RIC minimal implementation (demo coming once ready, might take still weeks)
        1. once it's somewhat usable, pls. place into subdirectory under ric-plt/ric-dep
    6. 2023-09-12:
      1. changes related to registration API needed in xapp-frame (problem still to be thought of)
      2. something not working in github: IT-25974 - again related to github replication.
    7. 2023-09-26
      1. Abhijit presented his work on a single near RT RIC helm chart and bringing up the platform on minikube on Ubuntu 22.04. We decided to proceed with this.
      2. github action problem with master vs g release for replication → ticket.
      3. Abhijit wanted to provide a video for new way of ric deployment
  9. Cap Gemini updates (subteam-cg)? 
    1. 2023-08-01
      1. Gunja to present conflict management design

      2. thinking about adding support for DU in E2T/E2M/RNIB in I release

    2. 2023-08-22:
      1. Gunja provided reviews for DU support. Nokia to reviewed and merged
        1.  https://gerrit.o-ran-sc.org/r/q/topic:%22Multiple+E2+Node+support%22 and  https://gerrit.o-ran-sc.org/r/q/topic:Multi_E2_Node

      2. Conflict detection and management. Presentation by Gunja on Sep-12 link-to-slideset
        1. Ashish S. (CapGemini) presented this.
        2. Thoralf will initiate a new repo for this: ric-plt/conflictmgr
          1. this might become an optional or mandatory (but default-disabled) component of thr near-rt ric platform.
          2. todo-cap-gemini: align usage of UE ID with wg3 discussion on this.
          3. additional latency comes only from guidance request
          4. xapp-framework could be extended to automatically do E2 guidance requests
    3. 2023-09-26:
      1. first step of new repo created, but still issues with initial files in repo. Thoralf raised request to LF: https://jira.linuxfoundation.org/plugins/servlet/desk/portal/2/IT-26015 
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. code changes, but difficult to test as difficult to change order of IEs in message.
    2. 2023-06-06: Added unit tests (integrated in image building) - did some changes in the stubs (based on environment variables). Next step looking into this.
    3. 2023-07-18: Code changes almost ready for RIC subscription response - gerrit review coming.
    4. 2023-08-22: feedback from Anssi on submgr received and incorporating these changes, but not yet in review.
    5. 2023-08-29: ready for merging once the CI problem (gofmt) is fixed. Can be merged together with a change in the helm chart (ric-dep). Default behavior is "strict order" (as currently). But config value can change to "any order".
  11. Dhiraj (subteam-r)
    1. 2023-07-18: IPv6 changes to come as review
    2. 2023-08-01: working on it.
    3. 2023-08-22:
      1. checking compliance/license issues
      2. How are policy types created? xApps register by policy type and understands the schema that is bound to it. Non-RT RIC should create policies using the same schema (there's a GUI for this on non-RT RIC side).
    4. 2023-08-29:
      1. got clarity on license issues and now waiting for internal approval before publishing ipv6 releated changes
  12. Alexandre (subteam-utfpr)
    1. 2023-08-22: Alexandre couldn't participate, but informed after the meeting by e-mail: "My plan for the next two weeks is to fix both RIC-989 and RIC-991 issues."
    2. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
    3. 2023-09-26: subscription message issue with encoding E2SM parts. A. will send e-mail to Thoralf
  13. Nokia (subteam-n)
    1. 2023-08-22: want to work on RIC-997
    2. 2023-09-12: Thoralf did changes to readthedocs in all near-RT RIC repos. LF informed (link) these changes are needed because some configuration parameters are being removed. No further changes needed due to this. Example: https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/11747. Note, though, that some repos don't currently generate read-the-docs documention. For the "A1" example, though you see a new documentation version in this URL: https://readthedocs.org/projects/o-ran-sc-ric-plt-a1/builds/
    3. Thoralf on holiday on Oct-10. Sunil?
  14. I release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for I release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. input for release candidates: left overs and generally open items, RSAC
    3. Sprint dates
      1. Sprint I release dev sprint 1: Aug-21 to Sep-10
      2. Sprint I release dev sprint 2: Sep-11 to Oct-1
      3. Sprint I release dev sprint 3: Oct-2 to Oct-22
      4. Sprint I release dev sprint 4: Oct-23 to Nov-12 (last planned development sprint)
      5. Sprint I release dev sprint 5: Nov-13 to Dec-3 (only for unplanned last-minute development items)
    4. Plan (v03 as of 2023-08-18):
      1. I release plan moved to I release page.
      2. E2 enhancements, incl. conflict mgmt.

        1. RIC-993 (CG): Near-RT RIC conflict management (*)

        2. RIC-933 (CG) : Adding support for DU in E2T/E2M/RNIB

        3. RIC-967 (CG) xApp-facing interface for subscription delete required (added on 2023-08-23)
        4. RIC-994 (S): Support for E2APv3.0

        5. RIC-995 (S): Support for RIC Query

        6. RIC-996 (S) Support for Subscription modifications (dhiraj interested as reviewer)

        7. RIC-387 (S): Support for E2 reset from RIC to RAN (completes also RIC-383) (prio1) (Dhiraj interested as reviewer, but we had earlier discussion on this)

        8. RIC-997 (N): Handling of RIC Error indication _during_ E2 setup

        9. RIC-963 (GS) modify src code to be more lenient in ordering of IEs in ASN.1

      3. Other

        1. RIC-998 (S): K8S operators for deploying/undeploy xApps(*(1))

        2. RIC-999 (S): A1 alignment with A1AP (still under investigation. Minimum is using correct URL) (*(1))

        3. RIC-954 (S): DMS Rest API support for deleting/undeploy xApps (DMS REST is 2nd ifc addressing same space as dmscli) (1)

        4. Already in H: RIC-985 (UTFPR) IPv6 support for RMR 

        5. RIC-1000 (R): Support for only-IPv6 in RIC-internal interfaces

        6. RIC-1004 (AG): Xapp Rust Framework enhancement after initial basic Xapp Framework Support
  1. RICAPP agenda: RICAPP Meetings.

2023-09-12

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame/+/10923 OK, module version updates only
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-05-23:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1011 (Nokia fixes) E2 error with cause duplicate-error for all subscriptions requests after resource-limit failure
    2. RIC-1009 E2Mgr API can be improperly invoked → convert to bigger Epic?
    3. RIC-1002 (Nokia fixes) Abnormal signaling process cause E2Term crash (this could be a security issue)
    4. RIC-1001 RMR service should verify route tables - Alexandre will take a look
    5. RIC-991 rmr related (not a duplicate) - Alexandre will take a look
    6. RIC-989 rmr (minor) security issue - Alexandre will take a look
    7. RIC-979 (Abhijit will close this one) Decode Error with e2sim on e2term Pod - 2023-08-22: Abhijit still looking into this, but with latest Ubuntu packages this seems not to cause the problem anymore.
    8. RIC-972 (Naman) URL for A1 mediator to align with spec.
    9. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    10. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    11. RIC-915 dms_cli for installing xapp not working (raised by James)
    12. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    13. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    14. RIC-897 SCTP connection fails with Viavi // update with workaround → Thoralf changed this into an Epic (problem was on simulator side. But some useful extension on E2T comes from this as well)
    15. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    16. RIC-894 long idle period (days) causes RMR connection breaks
    17. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    18. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    19. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    20. RIC-837 RMR is not forwarding messages from E2T to E2M
    21. RIC-835 → 2021-12-07 no news from Viktor
    22. fixed: ...
  4. James: updates?
    1. 2023-08-01:
      1. O2 integration with OSC RIC is still pending with WR.
      2. OAI was discussed in last week's TOC, and it seems OAI license is not blocker for using OAI in OSC-labs.
    2. 2023-08-22:
      1. Can we do pair-wise testing, e.g., between (1) xapp and RIC, (2) non-RT RIC ↔ near-RT RIC testing (only A1) ?
        1. E.g., KPIMON or bouncer xApp could be used. Sunil might be able to help.
        2. e.g., existing discussion with John
    3. 2023-08-29: no news
    4. 2023-09-12: requested from PTLs pair-wise testing. From Near-RT RIC point of view we hope for the non-RT RIC project to initiate testing with A1 mediator standalone version.
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22 : could not participate
  6. Sunil updates (subteam-h)?
    1. 2023-07-18, 2023-08-01, 2023-08-22, 2023-08-29: no news
    2. 2023-09-12: can give update next time. Maybe 2 or 3 items to work on.
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-08-01:
      1. E2AP v3.0 → we took a look at what changes are coming 
      2. A1 enhancements
      3. considering upgrade of ubuntu and k8s
      4. deploying RIC and xapps using k8S operator I_Release_Proposal_Samsung_Naman.pptx
      5. DMS delete PI
      6. E2 reset from ric to e2 node
    2. 2023-08-22: we discussed Jira item priority.
    3. 2023-08-29: no news, other than Naman working on the operator implementation.
    4. 2023-09-12:
      1. We had a meeting with John and Denis on non-rt RIC compatibilty. Agreed in fixes for URL and policystatusobject type from integer→string (as per standard) → Naman.
      2. Thoralf to figure out a way to start A1 mediator standalone for CI testing
        1. Thoralf sent instructions to John
      3. current implementation of /data-delivery URL in A1 - need to check if >1 consumer of EI data (sent by non-RT RIC) works on our side.
      4. Naman also works on the operator implementation
  8. Abhijit updates (subteam-ag) ?
    1. 2023-05-23
        1. hw-rust xapp using xapp descriptor (config.json) works, but still fixing lifeness and readiness probe
        2. testing of subscriptions using hw-rust (facing the E2T problem)
    2. 2023-07-18: no news
    3. 2023-08-01: got logs from Subhash. Now ran into issues with Dockerfile in E2T (gcc related differences between ubuntu 20 and 22)
    4. 2023-08-22: next release item discussed and RIC-979
    5. 2023-08-29:
      1. created RIC-1004 for release I item.
      2. still working on RIC minimal implementation (demo coming once ready, might take still weeks)
        1. once it's somewhat usable, pls. place into subdirectory under ric-plt/ric-dep
    6. 2023-09-12:
      1. changes related to registration API needed in xapp-frame (problem still to be thought of)
      2. something not working in github: IT-25974 - again related to github replication.
  9. Cap Gemini updates (subteam-cg)? 
    1. 2023-08-01
      1. Gunja to present conflict management design

      2. thinking about adding support for DU in E2T/E2M/RNIB in I release

    2. 2023-08-22:
      1. Gunja provided reviews for DU support. Nokia to reviewed and merged
        1.  https://gerrit.o-ran-sc.org/r/q/topic:%22Multiple+E2+Node+support%22 and  https://gerrit.o-ran-sc.org/r/q/topic:Multi_E2_Node

      2. Conflict detection and management. Presentation by Gunja on Sep-12 link-to-slideset
        1. Ashish S. (CapGemini) presented this.
        2. Thoralf will initiate a new repo for this: ric-plt/conflictmgr
          1. this might become an optional or mandatory (but default-disabled) component of thr near-rt ric platform.
          2. todo-cap-gemini: align usage of UE ID with wg3 discussion on this.
          3. additional latency comes only from guidance request
          4. xapp-framework could be extended to automatically do E2 guidance requests
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. code changes, but difficult to test as difficult to change order of IEs in message.
    2. 2023-06-06: Added unit tests (integrated in image building) - did some changes in the stubs (based on environment variables). Next step looking into this.
    3. 2023-07-18: Code changes almost ready for RIC subscription response - gerrit review coming.
    4. 2023-08-22: feedback from Anssi on submgr received and incorporating these changes, but not yet in review.
    5. 2023-08-29: ready for merging once the CI problem (gofmt) is fixed. Can be merged together with a change in the helm chart (ric-dep). Default behavior is "strict order" (as currently). But config value can change to "any order".
  11. Dhiraj (subteam-r)
    1. 2023-07-18: IPv6 changes to come as review
    2. 2023-08-01: working on it.s
    3. 2023-08-22:
      1. checking compliance/license issues
      2. How are policy types created? xApps register by policy type and understands the schema that is bound to it. Non-RT RIC should create policies using the same schema (there's a GUI for this on non-RT RIC side).
    4. 2023-09-29:
      1. got clarity on license issues and now waiting for internal approval.
  12. Alexandre (subteam-utfpr)
    1. 2023-08-22: Alexandre couldn't participate, but informed after the meeting by e-mail: "My plan for the next two weeks is to fix both RIC-989 and RIC-991 issues."
    2. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
  13. Nokia (subteam-n)
    1. 2023-08-22: want to work on RIC-997
    2. 2023-09-12: Thoralf did changes to readthedocs in all near-RT RIC repos. LF informed (link) these changes are needed because some configuration parameters are being removed. No further changes needed due to this. Example: https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/11747. Note, though, that some repos don't currently generate read-the-docs documention. For the "A1" example, though you see a new documentation version in this URL: https://readthedocs.org/projects/o-ran-sc-ric-plt-a1/builds/
  14. I release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for I release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. input for release candidates: left overs and generally open items, RSAC
    3. Sprint dates
      1. Sprint I release dev sprint 1: Aug-21 to Sep-10
      2. Sprint I release dev sprint 2: Sep-11 to Oct-1
      3. Sprint I release dev sprint 3: Oct-2 to Oct-22
      4. Sprint I release dev sprint 4: Oct-23 to Nov-12 (last planned development sprint)
      5. Sprint I release dev sprint 5: Nov-13 to Dec-3 (only for unplanned last-minute development items)
    4. Plan (v03 as of 2023-08-18):
      1. E2 enhancements, incl. conflict mgmt.

        1. RIC-993 (CG): Near-RT RIC conflict management (*)

        2. RIC-933 (CG) : Adding support for DU in E2T/E2M/RNIB

        3. RIC-967 (CG) xApp-facing interface for subscription delete required (added on 2023-08-23)
        4. RIC-994 (S): Support for E2APv3.0

        5. RIC-995 (S): Support for RIC Query

        6. RIC-996 (S) Support for Subscription modifications (dhiraj interested as reviewer)

        7. RIC-387 (S): Support for E2 reset from RIC to RAN (completes also RIC-383) (prio1) (Dhiraj interested as reviewer, but we had earlier discussion on this)

        8. RIC-997 (N): Handling of RIC Error indication _during_ E2 setup

        9. RIC-963 (GS) modify src code to be more lenient in ordering of IEs in ASN.1

      2. Other

        1. RIC-998 (S): K8S operators for deploying/undeploy xApps(*(1))

        2. RIC-999 (S): A1 alignment with A1AP (still under investigation. Minimum is using correct URL) (*(1))

        3. RIC-954 (S): DMS Rest API support for deleting/undeploy xApps (DMS REST is 2nd ifc addressing same space as dmscli) (1)

        4. Already in H: RIC-985 (UTFPR) IPv6 support for RMR 

        5. RIC-1000 (R): Support for only-IPv6 in RIC-internal interfaces

        6. RIC-1004 (AG): Xapp Rust Framework enhancement after initial basic Xapp Framework Support
  1. RICAPP agenda: RICAPP Meetings.


2023-08-29 (back to normal week, therefore only 1 week after previous meeting)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame/+/10923 OK, module version updates only
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-05-23:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1002 Abnormal signaling process cause E2Term crash (this could be a security issue)
    2. RIC-1001 RMR service should verify route tables.
    3. RIC-991 rmr related (not a duplicate) - Alexandre will take a look
    4. RIC-989 rmr (minor) security issue - Alexandre will take a look
    5. RIC-979 Decode Error with e2sim on e2term Pod - 2023-08-22: Abhijit still looking into this, but with latest Ubuntu packages this seems not to cause the problem anymore.
    6. RIC-972 URL for A1 mediator to align with spec.
    7. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    8. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    9. RIC-915 dms_cli for installing xapp not working (raised by James)
    10. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    11. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    12. RIC-897 SCTP connection fails with Viavi // update with workaround → Thoralf changed this into an Epic (problem was on simulator side. But some useful extension on E2T comes from this as well)
    13. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    14. RIC-894 long idle period (days) causes RMR connection breaks
    15. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    16. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    17. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    18. RIC-837 RMR is not forwarding messages from E2T to E2M
    19. RIC-835 → 2021-12-07 no news from Viktor
    20. fixed: ...
  4. James: updates?
    1. 2023-08-01:
      1. O2 integration with OSC RIC is still pending with WR.
      2. OAI was discussed in last week's TOC, and it seems OAI license is not blocker for using OAI in OSC-labs.
    2. 2023-08-22:
      1. Can we do pair-wise testing, e.g., between (1) xapp and RIC, (2) non-RT RIC ↔ near-RT RIC testing (only A1) ?
        1. E.g., KPIMON or bouncer xApp could be used. Sunil might be able to help.
        2. e.g., existing discussion with John
    3. 2023-08-29: no news
  5. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22 : could not participate
  6. Sunil updates (subteam-h)?
    1. 2023-07-18, 2023-08-01, 2023-08-22, 2023-08-29: no news
  7. Subhash/Naman updates (subteam-s) ?
    1. 2023-08-01:
      1. E2AP v3.0 → we took a look at what changes are coming 
      2. A1 enhancements
      3. considering upgrade of ubuntu and k8s
      4. deploying RIC and xapps using k8S operator I_Release_Proposal_Samsung_Naman.pptx
      5. DMS delete PI
      6. E2 reset from ric to e2 node
    2. 2023-08-22: we discussed Jira item priority.
    3. 2023-08-29: no news, other than Naman working on the operator implementation.
  8. Abhijit updates (subteam-ag) ?
    1. 2023-05-23
        1. hw-rust xapp using xapp descriptor (config.json) works, but still fixing lifeness and readiness probe
        2. testing of subscriptions using hw-rust (facing the E2T problem)
    2. 2023-07-18: no news
    3. 2023-08-01: got logs from Subhash. Now ran into issues with Dockerfile in E2T (gcc related differences between ubuntu 20 and 22)
    4. 2023-08-22: next release item discussed and RIC-979
    5. 2023-08-29:
      1. created RIC-1004 for release I item.
      2. still working on RIC minimal implementation (demo coming once ready, might take still weeks)
        1. once it's somewhat usable, pls. place into subdirectory under ric-plt/ric-dep
  9. Cap Gemini updates (subteam-cg)? 
    1. 2023-08-01
      1. Gunja to present conflict management design

      2. thinking about adding support for DU in E2T/E2M/RNIB in I release

    2. 2023-08-22:
      1. Gunja provided reviews for DU support. Nokia to reviewed and merged
        1.  https://gerrit.o-ran-sc.org/r/q/topic:%22Multiple+E2+Node+support%22 and  https://gerrit.o-ran-sc.org/r/q/topic:Multi_E2_Node

      2. Conflict management status? Thoralf checked by e-mail after the meeting. Presentation by Gunja planned for Sep-12
  10. Himanshu (subteam-gs) would like to work on RIC-963
    1. code changes, but difficult to test as difficult to change order of IEs in message.
    2. 2023-06-06: Added unit tests (integrated in image building) - did some changes in the stubs (based on environment variables). Next step looking into this.
    3. 2023-07-18: Code changes almost ready for RIC subscription response - gerrit review coming.
    4. 2023-08-22: feedback from Anssi on submgr received and incorporating these changes, but not yet in review.
    5. 2023-08-29: ready for merging once the CI problem (gofmt) is fixed. Can be merged together with a change in the helm chart (ric-dep). Default behavior is "strict order" (as currently). But config value can change to "any order".
  11. Dhiraj (subteam-r)
    1. 2023-07-18: IPv6 changes to come as review
    2. 2023-08-01: working on it.
    3. 2023-08-22:
      1. checking compliance/license issues
      2. How are policy types created? xApps register by policy type and understands the schema that is bound to it. Non-RT RIC should create policies using the same schema (there's a GUI for this on non-RT RIC side).
    4. 2023-09-29:
      1. got clarity on license issues and now waiting for internal approval.
  12. Alexandre (subteam-utfpr)
    1. 2023-08-22: Alexandre couldn't participate, but informed after the meeting by e-mail: "My plan for the next two weeks is to fix both RIC-989 and RIC-991 issues."
    2. 2023-08-29: Alexandre working on RIC-989 and RIC-991. Will also take a look at RIC-1001
  13. Nokia (subteam-n)
    1. 2023-08-22: want to work on RIC-997
  14. I release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for I release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. input for release candidates: left overs and generally open items, RSAC
    3. Sprint dates
      1. Sprint I release dev sprint 1: Aug-21 to Sep-10
      2. Sprint I release dev sprint 2: Sep-11 to Oct-1
      3. Sprint I release dev sprint 3: Oct-2 to Oct-22
      4. Sprint I release dev sprint 4: Oct-23 to Nov-12 (last planned development sprint)
      5. Sprint I release dev sprint 5: Nov-13 to Dec-3 (only for unplanned last-minute development items)
    4. Plan (v03 as of 2023-08-18):
      1. E2 enhancements, incl. conflict mgmt.

        1. RIC-993 (CG): Near-RT RIC conflict management (*)

        2. RIC-933 (CG) : Adding support for DU in E2T/E2M/RNIB

        3. RIC-967 (CG) xApp-facing interface for subscription delete required (added on 2023-08-23)
        4. RIC-994 (S): Support for E2APv3.0

        5. RIC-995 (S): Support for RIC Query

        6. RIC-996 (S) Support for Subscription modifications (dhiraj interested as reviewer)

        7. RIC-387 (S): Support for E2 reset from RIC to RAN (completes also RIC-383) (prio1) (Dhiraj interested as reviewer, but we had earlier discussion on this)

        8. RIC-997 (N): Handling of RIC Error indication _during_ E2 setup

        9. RIC-963 (GS) modify src code to be more lenient in ordering of IEs in ASN.1

      2. Other

        1. RIC-998 (S): K8S operators for deploying/undeploy xApps(*(1))

        2. RIC-999 (S): A1 alignment with A1AP (still under investigation. Minimum is using correct URL) (*(1))

        3. RIC-954 (S): DMS Rest API support for deleting/undeploy xApps (DMS REST is 2nd ifc addressing same space as dmscli) (1)

        4. Already in H: RIC-985 (UTFPR) IPv6 support for RMR 

        5. RIC-1000 (R): Support for only-IPv6 in RIC-internal interfaces

        6. RIC-1004 (AG): Xapp Rust Framework enhancement after initial basic Xapp Framework Support
  1. RICAPP agenda: RICAPP Meetings.

2023-08-22 (exceptionally one week later than normal)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame/+/10923 OK, module version updates only
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-05-23:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-1002 Abnormal signaling process cause E2Term crash (this could be a security issue)
    2. RIC-1001 RMR service should verify route tables.
    3. RIC-991 rmr related (not a duplicate) - Alexandre will take a look
    4. RIC-989 rmr (minor) security issue - Alexandre will take a look
    5. new: RIC-988 CLOSED e2 component configuration → Duplicate of fix https://gerrit.o-ran-sc.org/r/gitweb?p=ric-plt/e2mgr.git;a=commit;h=d2f1a29d3f1cc779045148a82729f644e6110776 
    6. RIC-986 ping-pong example xapp-frame-py needs fixes in the dockerfile DONE
    7. RIC-979 Decode Error with e2sim on e2term Pod - 2023-08-22: Abhijit still looking into this, but with latest Ubuntu packages this seems not to cause the problem anymore.
    8. RIC-972 URL for A1 mediator to align with spec.
    9. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    10. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    11. RIC-915 dms_cli for installing xapp not working (raised by James)
    12. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    13. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    14. RIC-897 SCTP connection fails with Viavi // update with workaround → Thoralf changed this into an Epic (problem was on simulator side. But some useful extension on E2T comes from this as well)
    15. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    16. RIC-894 long idle period (days) causes RMR connection breaks
    17. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    18. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    19. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    20. RIC-837 RMR is not forwarding messages from E2T to E2M
    21. RIC-835 → 2021-12-07 no news from Viktor
    22. fixed: RIC-986
  4. Himanshu: demo on the OAI CU <--> OSC RIC integration
    1. Himanshu presented the integration of SDRAN-fork of OAI (with SDRAN E2 support added) and how the CU connects to OSC RIC
  5. James: updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14, 2023-03-28 : no news
    3. 2023-04-11: H release test cases related O2 IMS committed into it/test. Some of these related to existing robot test cases.
    4. 2023-04-25: no updates
    5. 2023-05-09:
      1. Q-to-James: summary of what you presented in TOC (1 min) and let's raise question to all for input to integration project.
        1. Xtesting is used in integration project now (already for 6 months or so). Xtesting works also with robot test cases.
        2. James working in this integration for the test cases that are already in it/test. Infrastructure team also contributed O2 releated robot test cases (requires o-loud).
        3. Input from other subprojects, incl. our near-RT RIC project?
      2. James needs some hints on how to run the existing robot test cases in it/test related to missing env variables: GLOBAL_INJECTED_E2MGR_USER and APPMGR_ENDPOINT.
    6. 2023-05-23 → no news
    7. 2023-07-18: James' focus is currently on OSC & OAI cooperation. Current thinking is to use Taiwan lab to host OAI -based installation over E2AP (2.0). See also https://openairinterface.org/mosaic5g/
      1. usage of robot test cases (from it/test) is still something that James is thinking about.
      2. Himanshu commented that he tried OAI CU/DU with OSC RIC and KPM xApp.
    8. 2023-08-01:
      1. O2 integration with OSC RIC is still pending with WR.
      2. OAI was discussed in last week's TOC, and it seems OAI license is not blocker for using OAI in OSC-labs.
    9. 2023-08-22:
      1. Can we do pair-wise testing, e.g., between (1) xapp and RIC, (2) non-RT RIC ↔ near-RT RIC testing (only A1) ?
        1. E.g., KPIMON or bouncer xApp could be used. Sunil might be able to help.
        2. e.g., existing discussion with John
  6. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-08-22 : could not participate
  7. Sunil updates (subteam-h)?
    1. 2023-07-18, 2023-08-01, 2023-08-22: no news
  8. Subhash/Naman updates (subteam-s) ?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
        2. Integration with AI/ML project: kserve_adapter
          1. data pipeline (Hoejoo's e-mail)
            1. 2023-01-31 not discussed in today's meeting
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work
    3. 2023-03-28: work continues
    4. 2023-04-11: E2 reset work in submgr is now under work.
    5. 2023-04-25: Naman working on E2 reset (submgr part), ricdms not too much progress. no update on kserve
    6. 2023-05-09:
      1. E2 reset done, but still one more review coming on submgr to block subscriptions fo0r E2 nodes under reset.
      2. A1 bug fixes being almost ready.
      3. A1 mediator nanobot might be delayed.
      4. AI/ML adapter work is still ongoing - ricdms changes still coming during next 1-2 weeks.
    7. 2023-05-23
      1. E2 reset (from E2 node): done
      2. KServe adapter still being worked on.
      3. nanobot integration still being worked on.
    8. 2023-07-18: no news, planning for I release
    9. 2023-08-01:
      1. E2AP v3.0 → we took a look at what changes are coming 
      2. A1 enhancements
      3. considering upgrade of ubuntu and k8s
      4. deploying RIC and xapps using k8S operator I_Release_Proposal_Samsung_Naman.pptx
      5. DMS delete PI
      6. E2 reset from ric to e2 node
    10. 2023-08-22: we discussed Jira item priority.
  9. Abhijit updates (subteam-ag) ?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14:now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
    3. 2023-03-28: working on RIC-969 and part of RIC-957
    4. 2023-04-11:
      1. RIC-969 first set of APIs (SDL) implemented. RNIB not yet (also under RIC-969).
      2. hw world xApp should grow with the implementation of xapp-frame-rust. Initial hw-rust xapp will show use of SDL/RNIB.
    5. 2023-04-25
      1. working on RNIB support in rust (https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10906) and next step hw-rust.
    6. 2023-05-09
      1. RIC-977 (subscription API) - pls. merge.
      2. RIC-978 pls. try to complete during this week.
      3. issues with E2 simulator → to get in contact with Naman and Subhash
    7. 2023-05-23
      1. hw-rust xapp using xapp descriptor (config.json) works, but still fixing lifeness and readiness probe
      2. testing of subscriptions using hw-rust (facing the E2T problem)
    8. 2023-07-18: no news
    9. 2023-08-01: got logs from Subhash. Now ran into issues with Dockerfile in E2T (gcc related differences between ubuntu 20 and 22)
    10. 2023-08-22: next release item discussed and RIC-979
  10. Cap Gemini updates (subteam-cg)? 
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
    2. 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-23: no news.
    3. 2023-05-23: presentation on RIC SUBSCRIPTION DELETE REQUIRED and communication between xApps and submgr. → DONE
    4. 2023-07-18: Cap Gemini (Gunja) conflict management presentation planned for end of July
    5. 2023-08-01
      1. Gunja to present conflict management design

      2. thinking about adding support for DU in E2T/E2M/RNIB in I release

    6. 2023-08-22:
      1. Gunja provided reviews for DU support. Nokia to reviewed and merged
        1.  https://gerrit.o-ran-sc.org/r/q/topic:%22Multiple+E2+Node+support%22 and  https://gerrit.o-ran-sc.org/r/q/topic:Multi_E2_Node

      2. conflit management status?
  11. Himanshu (subteam-gs) would like to work on RIC-963
    1. code changes, but difficult to test as difficult to change order of IEs in message.
    2. 2023-06-06: Added unit tests (integrated in image building) - did some changes in the stubs (based on environment variables). Next step looking into this.
    3. 2023-07-18: Code changes almost ready for RIC subscription response - gerrit review coming.
    4. 2023-08-22: feedback from Anssi on submgr received and incorporating these changes, but not yet in review.
  12. Dhiraj (subteam-r)
    1. 2023-05-23: ipv6 - Alexandre working on this: RIC-985. Note that this requires re-creation of most container images.
    2. 2023-06-06: ipv6 fix is merged. Dhiraj tried with this new version. Containers start. Good. Investigation continues - most likely fix needed in routing manager ([ brackets cause issues)and E2T (crashes to be fixed).
    3. 2023-07-18: IPv6 changes to come as review
    4. 2023-08-01: working on it.
    5. 2023-08-22:
      1. checking compliance/license issues
      2. How are policy types created? xApps register by policy type and understands the schema that is bound to it. Non-RT RIC should create policies using the same schema (there's a GUI for this on non-RT RIC side).
  13. Alexandre (subteam-utfpr)
    1. 2023-05-23: no news
    2. 2023-06-06:
      1. fixed IPv6 support in RMR - works in IPv6 only case and in case of providing specific IPv6 address. Routing mgr might require additional work.
      2. seems also to be a bug in interface name solution in RMR. Remember to create a JIRA item (RIC-987)
    3. 2023-08-22: Alexandre couldn't participate, but informed after the meeting by e-mail: "My plan for the next two weeks is to fix both RIC-989 and RIC-991 issues."
  14. Nokia (subteam-n)
    1. GRPC vs RMR
      1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
      2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09, 2023-05-23, 2023-07-18: no update
    2. 2023-08-22: want to work on RIC-997
  15. I release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for I release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. input for release candidates: left overs and generally open items, RSAC
    3. Sprint dates
      1. Sprint I release dev sprint 1: Aug-21 to Sep-10
      2. Sprint I release dev sprint 2: Sep-11 to Oct-1
      3. Sprint I release dev sprint 3: Oct-2 to Oct-22
      4. Sprint I release dev sprint 4: Oct-23 to Nov-12 (last planned development sprint)
      5. Sprint I release dev sprint 5: Nov-13 to Dec-3 (only for unplanned last-minute development items)
    4. Plan (v03 as of 2023-08-18): link
      1. E2 enhancements, incl. conflict mgmt.

        1. RIC-993 (CG): Near-RT RIC conflict management (*)

        2. RIC-933 (CG) : Adding support for DU in E2T/E2M/RNIB

        3. RIC-994 (S): Support for E2APv3.0

        4. RIC-995 (S): Support for RIC Query

        5. RIC-996 (S) Support for Subscription modifications (dhiraj interested as reviewer)

        6. RIC-387 (S): Support for E2 reset from RIC to RAN (completes also RIC-383) (prio1) (dhiraj interested as reviewer, but we had earlier discussion on this)

        7. RIC-997 (N): Handling of RIC Error indication _during_ E2 setup

        8. RIC-963 (GS)modify src code to be more lenient in ordering of IEs in ASN.1

      2. Other

        1. RIC-998 (S): K8S operators for deploying/undeploy xApps(*(1))

        2. RIC-999 (S): A1 alignment with A1AP (still under investigation. Minimum is using correct URL) (*(1))

        3. RIC-954 (S): DMS Rest API support for deleting/undeploy xApps (DMS REST is 2nd ifc addressing same space as dmscli) (1)

        4. Already in H: RIC-985 (UTFPR) IPv6 support for RMR 

        5. RIC-1000 (R): Support for only-IPv6 in RIC-internal interfaces

        6. Abhijit will create issue and send e-mail
  1. RICAPP agenda: RICAPP Meetings.

2023-08-01

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame/+/10923 OK, module version updates only
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-05-23:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. new: RIC-991 rmr related (not a duplicate) - Alexandre will take a look
    2. new: RIC-989 rmr (minor) security issue - Alexandre will take a look
    3. new: RIC-988 CLOSED e2 component configuration → Duplicate of fix https://gerrit.o-ran-sc.org/r/gitweb?p=ric-plt/e2mgr.git;a=commit;h=d2f1a29d3f1cc779045148a82729f644e6110776 
    4. RIC-986 ping-pong example xapp-frame-py needs fixes in the dockerfile
    5. RIC-979 Decode Error with e2sim on e2term Pod - AP-Subhash/Naman add logs
    6. RIC-972 URL for A1 mediator to align with spec.
    7. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    8. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    9. RIC-915 dms_cli for installing xapp not working (raised by James)
    10. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    11. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    12. RIC-897 SCTP connection fails with Viavi // update with workaround
    13. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    14. RIC-894 long idle period (days) causes RMR connection breaks
    15. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    16. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    17. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    18. RIC-837 RMR is not forwarding messages from E2T to E2M
    19. RIC-835 → 2021-12-07 no news from Viktor
    20. fixed:
  4. Himanshu: demo on the OAI CU <--> OSC RIC integration
    1. Himanshu presented the integration of SDRAN-fork of OAI (with SDRAN E2 support added) and how the CU connects to OSC RIC
  5. James: updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14, 2023-03-28 : no news
    3. 2023-04-11: H release test cases related O2 IMS committed into it/test. Some of these related to existing robot test cases.
    4. 2023-04-25: no updates
    5. 2023-05-09:
      1. Q-to-James: summary of what you presented in TOC (1 min) and let's raise question to all for input to integration project.
        1. Xtesting is used in integration project now (already for 6 months or so). Xtesting works also with robot test cases.
        2. James working in this integration for the test cases that are already in it/test. Infrastructure team also contributed O2 releated robot test cases (requires o-loud).
        3. Input from other subprojects, incl. our near-RT RIC project?
      2. James needs some hints on how to run the existing robot test cases in it/test related to missing env variables: GLOBAL_INJECTED_E2MGR_USER and APPMGR_ENDPOINT.
    6. 2023-05-23 → no news
    7. 2023-07-18: James' focus is currently on OSC & OAI cooperation. Current thinking is to use Taiwan lab to host OAI -based installation over E2AP (2.0). See also https://openairinterface.org/mosaic5g/
      1. usage of robot test cases (from it/test) is still something that James is thinking about.
      2. Himanshu commented that he tried OAI CU/DU with OSC RIC and KPM xApp.
    8. 2023-08-01:
      1. O2 integration with OSC RIC is still pending with WR.
      2. OAI was discussed in last week's TOC, and it seems OAI license is not blokcer for using OAI in OSC-labs.
  6. Prashant's work in near-RT RIC(subteam-p)
    1. 2023-04-25:
      1. Prashant updated call flow for A1 polciy status update. Will send it for review RIC-973.
      2. Prashant, pls. create JIRA item for the Golang implementation related to policytypes: RIC-975 → DONE
      3. Prashant, pls. create JIRA item for the SCTP E2 timeout change.  RIC-976 Three reviews, but only one is valid
    2. 2023-05-09
      1. question related to O1 (for stats handling without Vespa) - see RIC-798
    3. 2023-05-23
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/11127?usp=search and two more minor ones to be reviewed Naman/Subhash during this week
      2. E2 → Alexandre to review - 2023-06-06: merged
    4. 2023-06-06: Prashant posted in O-RAN WG3 on O1 a question related on the why of notifications + SFTP. No reply yet.
      1. 2023-07-18: feedback was that this is a 3GPP issue. Not further following up on this.
    5. 2023-06-18: Thoralf-AP: remove all items above as they are done
  7. Sunil updates (subteam-h)?
    1. 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09: no news
    2. 2023-05-23: all items from HCL to be moved to I release.
    3. 2023-07-18, 2023-08-01: no news
  8. Subhash/Naman updates (subteam-s) ?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
        2. Integration with AI/ML project: kserve_adapter
          1. data pipeline (Hoejoo's e-mail)
            1. 2023-01-31 not discussed in today's meeting
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work
    3. 2023-03-28: work continues
    4. 2023-04-11: E2 reset work in submgr is now under work.
    5. 2023-04-25: Naman working on E2 reset (submgr part), ricdms not too much progress. no update on kserve
    6. 2023-05-09:
      1. E2 reset done, but still one more review coming on submgr to block subscriptions fo0r E2 nodes under reset.
      2. A1 bug fixes being almost ready.
      3. A1 mediator nanobot might be delayed.
      4. AI/ML adapter work is still ongoing - ricdms changes still coming during next 1-2 weeks.
    7. 2023-05-23
      1. E2 reset (from E2 node): done
      2. KServe adapter still being worked on.
      3. nanobot integration still being worked on.
    8. 2023-07-18: no news, planning for I release
    9. 2023-08-01:
      1. E2AP v3.0 → we took a look at what changes are coming
      2. A1 enhancements
      3. considering upgrade of ubuntu and k8s
      4. deploying RIC and xapps using k8S operator
      5. DMS delete PI
      6. E2 reset from ric to e2 node
  9. Abhijit updates (subteam-ag) ?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14:now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
    3. 2023-03-28: working on RIC-969 and part of RIC-957
    4. 2023-04-11:
      1. RIC-969 first set of APIs (SDL) implemented. RNIB not yet (also under RIC-969).
      2. hw world xApp should grow with the implementation of xapp-frame-rust. Initial hw-rust xapp will show use of SDL/RNIB.
    5. 2023-04-25
      1. working on RNIB support in rust (https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10906) and next step hw-rust.
    6. 2023-05-09
      1. RIC-977 (subscription API) - pls. merge.
      2. RIC-978 pls. try to complete during this week.
      3. issues with E2 simulator → to get in contact with Naman and Subhash
    7. 2023-05-23
      1. hw-rust xapp using xapp descriptor (config.json) works, but still fixing lifeness and readiness probe
      2. testing of subscriptions using hw-rust (facing the E2T problem)
    8. 2023-07-18: no news
    9. 2023-08-01: got logs from Subhash. Now ran into issues with Dockerfile in E2T (gcc related differences between ubuntu 20 and 22)
  10. Cap Gemini updates (subteam-cg)? 
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
    2. 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-23: no news.
    3. 2023-05-23: presentation on RIC SUBSCRIPTION DELETE REQUIRED and communication between xApps and submgr. → DONE
    4. 2023-07-18: Cap Gemini (Gunja) conflict management presentation planned for end of July
    5. 2023-08-01
      1. Gunja to present conflict management design

      2. thinking about adding support for DU in E2T/E2M/RNIB in I release

  11. Himanshu (subteam-gs) would like to work on RIC-963
    1. code changes, but difficult to test as difficult to change order of IEs in message.
    2. 2023-06-06: Added unit tests (integrated in image building) - did some changes in the stubs (based on environment variables). Next step looking into this.
    3. 2023-07-18: Code changes almost ready for RIC subscription response - gerrit review coming.
    4. 2023-08-01: feedback from Anssi on submgr received and incorporating these changes.
  12. Dhiraj (subteam-r)
    1. 2023-05-23: ipv6 - Alexandre working on this: RIC-985. Note that this requires re-creation of most container images.
    2. 2023-06-06: ipv6 fix is merged. Dhiraj tried with this new version. Containers start. Good. Investigation continues - most likely fix needed in routing manager ([ brackets cause issues)and E2T (crashes to be fixed).
    3. 2023-07-18: IPv6 changes to come as review
    4. 2023-08-01: working on it.
  13. Alexandre (subteam-utfpr)
    1. 2023-05-23: no news
    2. 2023-06-06:
      1. fixed IPv6 support in RMR - works in IPv6 only case and in case of providing specific IPv6 address. Routing mgr might require additional work.
      2. seems also to be a bug in interface name solution in RMR. Remember to create a JIRA item
  14. Nokia(subteam-n)
    1. GRPC vs RMR
      1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
      2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09, 2023-05-23, 2023-07-18: no update
  15. I release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for I release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. input for release candidates: left overs and generally open items, RSAC
    3. Sprint dates
      1. Sprint G release dev sprint 1: Aug-21 to Sep-10
      2. Sprint G release dev sprint 2: Sep-11 to Oct-1
      3. Sprint G release dev sprint 3: Oct-2 to Oct-22
      4. Sprint G release dev sprint 4: Oct-23 to Nov-12 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-13 to Dec-3 (only for unplanned last-minute development items)
    4. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
    5. 2023-07-18: Naman proposed E2APv3.0 update and some A1 changes
      1. E2APv3.0 changes for existing functionality (possible item for release I) - to be sent by e-mail.
        1. Dhiraj to be involved.
      2. Changes for A1 to achieve spec compliance (for the URL change we could do it in a backwards compatible way)
      3. E2 Reset from RIC to RAN
    6. 2023-07-18: (Dhiraj) IPv6 changes
    7. 2023-07-18: (Thoralf) RIC Error indication during E2 setup
    8. 2023-07-18: (Dhiraj) (not committed, but can prepare a list on where dynamic log level change is missing)
    9. 2023-08-01: Summary of plans:
      1. E2-related

        1. Near-RT RIC conflict management

        2. Adding support for DU in E2T/E2M/RNIB

        3. Support for E2APv3.0

        4. Support for RIC Query

        5. Support for Subscription modifications

        6. Support for E2 reset from RIC to RAN

        7. Handling of RIC Error indication _during_ E2 setup.

        8. RIC-963 modify src code to be more lenient in ordering of IEs in ASN.1

      2. Other

        1. K8S operators for deploying xApps

        2. A1 alignment with A1AP (still under investigation. Minimum is using correct URL)

        3. DMS Rest API support for deleting/undeploy xApps (DMS REST is 2nd ifc addressing same space as dmscli)

        4. IPv6 support for RMR

        5. Support for only-IPv6 in RIC-internal interfaces

  16. RICAPP agenda: RICAPP Meetings.

2023-07-18

Recording: link to zoom recording


  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame/+/10923 OK, module version updates only
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-05-23:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. new: RIC-989 rmr (minor) security issue
    2. new: RIC-988 CLOSED e2 component configuration → Duplicate of fix https://gerrit.o-ran-sc.org/r/gitweb?p=ric-plt/e2mgr.git;a=commit;h=d2f1a29d3f1cc779045148a82729f644e6110776 
    3. RIC-986 ping-pong example xapp-frame-py needs fixes in the dockerfile
    4. RIC-979 Decode Error with e2sim on e2term Pod - AP-Subhash/Naman add logs
    5. RIC-972 URL for A1 mediator to align with spec.
    6. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    7. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    8. RIC-915 dms_cli for installing xapp not working (raised by James)
    9. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    10. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    11. RIC-897 SCTP connection fails with Viavi // update with workaround
    12. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    13. RIC-894 long idle period (days) causes RMR connection breaks
    14. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    15. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    16. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    17. RIC-837 RMR is not forwarding messages from E2T to E2M
    18. RIC-835 → 2021-12-07 no news from Viktor
    19. fixed:
  4. James: updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14, 2023-03-28 : no news
    3. 2023-04-11: H release test cases related O2 IMS committed into it/test. Some of these related to existing robot test cases.
    4. 2023-04-25: no updates
    5. 2023-05-09:
      1. Q-to-James: summary of what you presented in TOC (1 min) and let's raise question to all for input to integration project.
        1. Xtesting is used in integration project now (already for 6 months or so). Xtesting works also with robot test cases.
        2. James working in this integration for the test cases that are already in it/test. Infrastructure team also contributed O2 releated robot test cases (requires o-loud).
        3. Input from other subprojects, incl. our near-RT RIC project?
      2. James needs some hints on how to run the existing robot test cases in it/test related to missing env variables: GLOBAL_INJECTED_E2MGR_USER and APPMGR_ENDPOINT.
    6. 2023-05-23 → no news
    7. 2023-07-18: James' focus is currently on OSC & OAI cooperation. Current thinking is to use Taiwan lab to host OAI -based installation over E2AP (2.0). See also https://openairinterface.org/mosaic5g/
      1. usage of robot test cases (from it/test) is still something that James is thinking about.
      2. Himanshu commented that he tried OAI CU/DU with OSC RIC and KPM xApp.
  5. Prashant's work in near-RT RIC
    1. 2023-04-25:
      1. Prashant updated call flow for A1 polciy status update. Will send it for review RIC-973.
      2. Prashant, pls. create JIRA item for the Golang implementation related to policytypes: RIC-975 → DONE
      3. Prashant, pls. create JIRA item for the SCTP E2 timeout change.  RIC-976 Three reviews, but only one is valid
    2. 2023-05-09
      1. question related to O1 (for stats handling without Vespa) - see RIC-798
    3. 2023-05-23
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/11127?usp=search and two more minor ones to be reviewed Naman/Subhash during this week
      2. E2 → Alexandre to review - 2023-06-06: merged
    4. 2023-06-06: Prashant posted in O-RAN WG3 on O1 a question related on the why of notifications + SFTP. No reply yet.
      1. 2023-07-18: feedback was that this is a 3GPP issue. Not further following up on this.
    5. 2023-06-18: Thoralf-AP: remove all items above as they are done
  6. Sunil updates?
    1. 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09: no news
    2. 2023-05-23: all items from HCL to be moved to I release.
    3. 2023-07-18: no news
  7. Subhash/Naman updates?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
        2. Integration with AI/ML project: kserve_adapter
          1. data pipeline (Hoejoo's e-mail)
            1. 2023-01-31 not discussed in today's meeting
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work
    3. 2023-03-28: work continues
    4. 2023-04-11: E2 reset work in submgr is now under work.
    5. 2023-04-25: Naman working on E2 reset (submgr part), ricdms not too much progress. no update on kserve
    6. 2023-05-09:
      1. E2 reset done, but still one more review coming on submgr to block subscriptions fo0r E2 nodes under reset.
      2. A1 bug fixes being almost ready.
      3. A1 mediator nanobot might be delayed.
      4. AI/ML adapter work is still ongoing - ricdms changes still coming during next 1-2 weeks.
    7. 2023-05-23
      1. E2 reset (from E2 node): done
      2. KServe adapter still being worked on.
      3. nanobot integration still being worked on.
    8. 2023-07-18: no news, planning for I release
  8. Abhijit updates?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14:now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
    3. 2023-03-28: working on RIC-969 and part of RIC-957
    4. 2023-04-11:
      1. RIC-969 first set of APIs (SDL) implemented. RNIB not yet (also under RIC-969).
      2. hw world xApp should grow with the implementation of xapp-frame-rust. Initial hw-rust xapp will show use of SDL/RNIB.
    5. 2023-04-25
      1. working on RNIB support in rust (https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10906) and next step hw-rust.
    6. 2023-05-09
      1. RIC-977 (subscription API) - pls. merge.
      2. RIC-978 pls. try to complete during this week.
      3. issues with E2 simulator → to get in contact with Naman and Subhash
    7. 2023-05-23
      1. hw-rust xapp using xapp descriptor (config.json) works, but still fixing lifeness and readiness probe
      2. testing of subscriptions using hw-rust (facing the E2T problem)
    8. 2023-07-18: no news
  9. Cap Gemini updates? 
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
    2. 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-23: no news.
    3. 2023-05-23: presentation on RIC SUBSCRIPTION DELETE REQUIRED and communication between xApps and submgr. → DONE
    4. 2023-07-18: Cap Gemini (Gunja) conflict management presentation planned for end of July
  10. Himanshu would like to work on RIC-963
    1. code changes, but difficult to test as difficult to change order of IEs in message.
    2. 2023-06-06: Added unit tests (integrated in image building) - did some changes in the stubs (based on environment variables). Next step looking into this.
    3. 2023-07-18: Code changes almost ready for RIC subscription response - gerrit review coming.
  11. Dhiraj
    1. 2023-05-23: ipv6 - Alexandre working on this: RIC-985. Note that this requires re-creation of most container images.
    2. 2023-06-06: ipv6 fix is merged. Dhiraj tried with this new version. Containers start. Good. Investigation continues - most likely fix needed in routing manager ([ brackets cause issues)and E2T (crashes to be fixed).
    3. 2023-07-18: IPv6 changes to come as review
  12. Alexandre
    1. 2023-05-23: no news
    2. 2023-06-06:
      1. fixed IPv6 support in RMR - works in IPv6 only case and in case of providing specific IPv6 address. Routing mgr might require additional work.
      2. seems also to be a bug in interface name solution in RMR. Remember to cretae a JIRA item
  13. I release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for I release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. input for release candidates: left overs and generally open items, RSAC
    3. Sprint dates
      1. Sprint G release dev sprint 1: Aug-21 to Sep-10
      2. Sprint G release dev sprint 2: Sep-11 to Oct-1
      3. Sprint G release dev sprint 3: Oct-2 to Oct-22
      4. Sprint G release dev sprint 4: Oct-23 to Nov-12 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-13 to Dec-3 (only for unplanned last-minute development items)
    4. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
    5. 2023-07-18: Naman proposed E2APv3.0 update and some A1 changes
      1. E2APv3.0 changes for existing functionality (possible item for release I) - to be sent by e-mail.
        1. Dhiraj to be involved.
      2. Changes for A1 to achieve spec compliance (for the URL change we could do it in a backwards compatible way)
      3. E2 Reset from RIC to RAN
    6. 2023-07-18: (Dhiraj) IPv6 changes
    7. 2023-07-18: (Thoralf) RIC Error indication during E2 setup
    8. 2023-07-18: (Dhiraj) (not committed, but can prepare a list on where dynamic log level change is missing)
  14. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09, 2023-05-23, 2023-07-18: no update
  15. RICAPP agenda: RICAPP Meetings.

2023-07-04

Since neither Thoralf nor Sunil can host this meeting it is cancelled.

2023-06-20

we did the demo meeting in the timeslot: link

2023-06-06

Recording: partial-only: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame/+/10923 OK, module version updates only
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-05-23:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-986 ping-pong example xapp-frame-py needs fixes in the dockerfile
    2. RIC-979 Decode Error with e2sim on e2term Pod - AP-Subhash/Naman add logs
    3. RIC-974 done: Errors running example ping/pong application in `xapp-frame-py`, incl. new release of builder image. Can be closed after that.
    4. RIC-972 URL for A1 mediator to align with spec.
    5. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    6. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    7. RIC-915 dms_cli for installing xapp not working (raised by James)
    8. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    9. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    10. RIC-897 SCTP connection fails with Viavi // update with workaround
    11. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    12. RIC-894 long idle period (days) causes RMR connection breaks
    13. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    14. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    15. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    16. RIC-837 RMR is not forwarding messages from E2T to E2M
    17. RIC-835 → 2021-12-07 no news from Viktor
    18. fixed: RIC-974, RIC-980, RIC-981
  4. H release status page: H Release#Near-Real-timeRANIntelligentControllerPlatform(E2Interface)(RICPLT) → 2023-06-06 we checked the status
    1. Thoralf expects everything to be ready by Jun-22
  5. O-RAN SC end of release of near-RT RIC: Demo scheduled for 2 weeks from now: 2023-06-20 Release H
  6. Demo videos (Prashant, Subhash, Gunja) for O-RAN face-to-face to be ready this week: upload video here: Material for O-RAN June f2f in Osaka  Jinri will combine
  7. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
    6. 2023-02-14: No news yet, Thoralf received e-mail on this from James. Still to check.
    7. 2023-02-28: some e-mail discussion. Ball's on Bin Yang & James side. Subhash and Thoralf discussed this and Thoralf to call a meeting with Bin Yang, subhash, James, Thoralf.
    8. 2023-03-14: AP-James Meeting was held. We see use cases around deploying RIC platform using helm charts over O2; and deploying xApps over O2. For xApps the role of descriptor->helmcharts→k8s manifests in SMO is still missing. AP for James to check with SMO project on ASD (porting or making available "ricdms/dmscli" to SMO; kserve adapter also affected as it uses ricdms) and support for deploying using helm charts and James to discuss with RSAC. Bin-Yang wants to check how RIC can be deployed using helm charts only.
    9. 2023-03-28:no news
    10. 2023-04-11: Tacker team provided ideas on SMO architecture (in context of RSAC). No immediate action items for Near-RT RIC platform project
    11. 2023-04-25, 2023-05-09, 2023-05-23: no news
  8. James: updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14, 2023-03-28 : no news
    3. 2023-04-11: H release test cases related O2 IMS committed into it/test. Some of these related to existing robot test cases.
    4. 2023-04-25: no updates
    5. 2023-05-09:
      1. Q-to-James: summary of what you presented in TOC (1 min) and let's raise question to all for input to integration project.
        1. Xtesting is used in integration project now (already for 6 months or so). Xtesting works also with robot test cases.
        2. James working in this integration for the test cases that are already in it/test. Infrastructure team also contributed O2 releated robot test cases (requires o-loud).
        3. Input from other subprojects, incl. our near-RT RIC project?
      2. James needs some hints on how to run the existing robot test cases in it/test related to missing env variables: GLOBAL_INJECTED_E2MGR_USER and APPMGR_ENDPOINT.
    6. 2023-05-23 → no news
  9. Prashant's work in near-RT RIC
    1. 2023-04-25:
      1. Prashant updated call flow for A1 polciy status update. Will send it for review RIC-973.
      2. Prashant, pls. create JIRA item for the Golang implementation related to policytypes: RIC-975 → DONE
      3. Prashant, pls. create JIRA item for the SCTP E2 timeout change.  RIC-976 Three reviews, but only one is valid
    2. 2023-05-09
      1. question related to O1 (for stats handling without Vespa) - see RIC-798
    3. 2023-05-23
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/11127?usp=search and two more minor ones to be reviewed Naman/Subhash during this week
      2. E2 → Alexandre to review - 2023-06-06: merged
    4. 2023-06-06: Prashant posted in O-RAN WG3 on O1 a question related on the why of notifications + SFTP. No reply yet.
  10. Sunil updates?
    1. 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09: no news
    2. 2023-05-23: all items from HCL to be moved to I release.
  11. Subhash/Naman updates?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
        2. Integration with AI/ML project: kserve_adapter
          1. data pipeline (Hoejoo's e-mail)
            1. 2023-01-31 not discussed in today's meeting
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work
    3. 2023-03-28: work continues
    4. 2023-04-11: E2 reset work in submgr is now under work.
    5. 2023-04-25: Naman working on E2 reset (submgr part), ricdms not too much progress. no update on kserve
    6. 2023-05-09:
      1. E2 reset done, but still one more review coming on submgr to block subscriptions fo0r E2 nodes under reset.
      2. A1 bug fixes being almost ready.
      3. A1 mediator nanobot might be delayed.
      4. AI/ML adapter work is still ongoing - ricdms changes still coming during next 1-2 weeks.
    7. 2023-05-23
      1. E2 reset (from E2 node): done
      2. KServe adapter still being worked on.
      3. nanobot integration still being worked on.
  12. Abhijit updates?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14:now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
    3. 2023-03-28: working on RIC-969 and part of RIC-957
    4. 2023-04-11:
      1. RIC-969 first set of APIs (SDL) implemented. RNIB not yet (also under RIC-969).
      2. hw world xApp should grow with the implementation of xapp-frame-rust. Initial hw-rust xapp will show use of SDL/RNIB.
    5. 2023-04-25
      1. working on RNIB support in rust (https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10906) and next step hw-rust.
    6. 2023-05-09
      1. RIC-977 (subscription API) - pls. merge.
      2. RIC-978 pls. try to complete during this week.
      3. issues with E2 simulator → to get in contact with Naman and Subhash
    7. 2023-05-23
      1. hw-rust xapp using xapp descriptor (config.json) works, but still fixing lifeness and readiness probe
      2. testing of subscriptions using hw-rust (facing the E2T problem)
  13. Cap Gemini updates? 
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
    2. 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-23: no news.
    3. 2023-05-23: presentation on RIC SUBSCRIPTION DELETE REQUIRED and communication between xApps and submgr. → DONE
  14. Himanshu would like to work on RIC-963
    1. code changes, but difficult to test as difficult to change order of IEs in message.
    2. 2023-06-06: Added unit tests (integrated in image building) - did some changes in the stubs (based on environment variables). Next step looking into this.
  15. Dhiraj
    1. 2023-05-23: ipv6 - Alexandre working on this: RIC-985. Note that this requires re-creation of most container images.
    2. 2023-06-06: ipv6 fix is merged. Dhiraj tried with this new version. Containers start. Good. Investigation continues - most likely fix needed in routing manager ([ brackets cause issues)and E2T (crashes to be fixed). 
  16. Alexandre
    1. 2023-05-23: no news
    2. 2023-06-06:
      1. fixed IPv6 support in RMR - works in IPv6 only case and in case of providing specific IPv6 address. Routing mgr might require additional work.
      2. seems also to be a bug in interface name solution in RMR. Remember to cretae a JIRA item.
  17. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  18. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09, 2023-05-23: no update
  19. RICAPP agenda: RICAPP Meetings.


2023-05-23

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame/+/10923 OK, module version updates only
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2023-05-23:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-980 new-and-doneNaman Reading Configuration for rmr from config file
    2. RIC-981 new-and-doneNaman Missing health check checking the Db connection through SDL even when the a1 name space is not present in db
    3. RIC-979 Decode Error with e2sim on e2term Pod - AP-Subhash/Naman add logs
    4. RIC-974 done: Errors running example ping/pong application in `xapp-frame-py`, incl. new release of builder image. Can be closed after that.
    5. RIC-972 URL for A1 mediator to align with spec.
    6. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    7. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    8. RIC-915 dms_cli for installing xapp not working (raised by James)
    9. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    10. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    11. RIC-897 SCTP connection fails with Viavi // update with workaround
    12. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    13. RIC-894 long idle period (days) causes RMR connection breaks
    14. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    15. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    16. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    17. RIC-837 RMR is not forwarding messages from E2T to E2M
    18. RIC-835 → 2021-12-07 no news from Viktor
    19. fixed: RIC-974, RIC-980, RIC-981
  4. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
    6. 2023-02-14: No news yet, Thoralf received e-mail on this from James. Still to check.
    7. 2023-02-28: some e-mail discussion. Ball's on Bin Yang & James side. Subhash and Thoralf discussed this and Thoralf to call a meeting with Bin Yang, subhash, James, Thoralf.
    8. 2023-03-14: AP-James Meeting was held. We see use cases around deploying RIC platform using helm charts over O2; and deploying xApps over O2. For xApps the role of descriptor->helmcharts→k8s manifests in SMO is still missing. AP for James to check with SMO project on ASD (porting or making available "ricdms/dmscli" to SMO; kserve adapter also affected as it uses ricdms) and support for deploying using helm charts and James to discuss with RSAC. Bin-Yang wants to check how RIC can be deployed using helm charts only.
    9. 2023-03-28:no news
    10. 2023-04-11: Tacker team provided ideas on SMO architecture (in context of RSAC). No immediate action items for Near-RT RIC platform project
    11. 2023-04-25, 2023-05-09, 2023-05-23: no news
  5. Prashant's work in near-RT RIC
    1. 2023-04-25:
      1. Prashant updated call flow for A1 polciy status update. Will send it for review RIC-973.
      2. Prashant, pls. create JIRA item for the Golang implementation related to policytypes: RIC-975 → DONE
      3. Prashant, pls. create JIRA item for the SCTP E2 timeout change.  RIC-976 Three reviews, but only one is valid
    2. 2023-05-09
      1. question related to O1 (for stats handling without Vespa) - see RIC-798
    3. 2023-05-23
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/11127?usp=search and two more minor ones to be reviewed Naman/Subhash during this week
      2. E2 → Alexandre to review
  6. James: updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14, 2023-03-28 : no news
    3. 2023-04-11: H release test cases related O2 IMS committed into it/test. Some of these related to existing robot test cases.
    4. 2023-04-25: no updates
    5. 2023-05-09:
      1. Q-to-James: summary of what you presented in TOC (1 min) and let's raise question to all for input to integration project.
        1. Xtesting is used in integration project now (already for 6 months or so). Xtesting works also with robot test cases.
        2. James working in this integration for the test cases that are already in it/test. Infrastructure team also contributed O2 releated robot test cases (requires o-loud).
        3. Input from other subprojects, incl. our near-RT RIC project?
      2. James needs some hints on how to run the existing robot test cases in it/test related to missing env variables: GLOBAL_INJECTED_E2MGR_USER and APPMGR_ENDPOINT.
    6. 2023-05-23 → no news
  7. Sunil updates?
    1. 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09: no news
    2. 2023-05-23: all items from HCL to be moved to I release.
  8. Subhash/Naman updates?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
        2. Integration with AI/ML project: kserve_adapter
          1. data pipeline (Hoejoo's e-mail)
            1. 2023-01-31 not discussed in today's meeting
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work
    3. 2023-03-28: work continues
    4. 2023-04-11: E2 reset work in submgr is now under work.
    5. 2023-04-25: Naman working on E2 reset (submgr part), ricdms not too much progress. no update on kserve
    6. 2023-05-09:
      1. E2 reset done, but still one more review coming on submgr to block subscriptions fo0r E2 nodes under reset.
      2. A1 bug fixes being almost ready.
      3. A1 mediator nanobot might be delayed.
      4. AI/ML adapter work is still ongoing - ricdms changes still coming during next 1-2 weeks.
    7. 2023-05-23
      1. E2 reset (from E2 node): done
      2. KServe adapter still being worked on.
      3. nanobot integration still being worked on.
  9. Abhijit updates?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14:now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
    3. 2023-03-28: working on RIC-969 and part of RIC-957
    4. 2023-04-11:
      1. RIC-969 first set of APIs (SDL) implemented. RNIB not yet (also under RIC-969).
      2. hw world xApp should grow with the implementation of xapp-frame-rust. Initial hw-rust xapp will show use of SDL/RNIB.
    5. 2023-04-25
      1. working on RNIB support in rust (https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10906) and next step hw-rust.
    6. 2023-05-09
      1. RIC-977 (subscription API) - pls. merge.
      2. RIC-978 pls. try to complete during this week.
      3. issues with E2 simulator → to get in contact with Naman and Subhash
    7. 2023-05-23
      1. hw-rust xapp using xapp descriptor (config.json) works, but still fixing lifeness and readiness probe
      2. testing of subscriptions using hw-rust (facing the E2T problem)
  10. Cap Gemini updates? 
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
    2. 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-23: no news.
    3. 2023-05-23: presentation on RIC SUBSCRIPTION DELETE REQUIRED and communication between xApps and submgr. → DONE
  11. Himanshu would like to work on RIC-963
    1. code changes, but difficult to test as difficult to change order of IEs in message.
  12. Dhiraj
    1. 2023-05-23: ipv6 - Alexandre working on this: RIC-985. Note that this requires re-creation of most container images.
  13. Alexandre
    1. 2023-05-23: no news
  14. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  15. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09, 2023-05-23: no update
  16. RICAPP agenda: RICAPP Meetings.


2023-05-09

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10906 OK tests included
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/10907 OK, tests included
      3. https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/11023 OK, tests included
      4. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10918 OK, as files are generated
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27, 2022-11-22, 2023-03-28, 2023-04-11:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-974 Errors running example ping/pong application in `xapp-frame-py`, incl. new release of builder image. Can be closed after that.
    2. RIC-972 URL for A1 mediator to align with spec.
    3. DONE: RIC-971 Fix potential segfaults and double free corruption (in E2T)
    4. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    5. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    6. RIC-915 dms_cli for installing xapp not working (raised by James)
    7. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    8. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    9. RIC-897 SCTP connection fails with Viavi // update with workaround
    10. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    11. RIC-894 long idle period (days) causes RMR connection breaks
    12. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    13. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    14. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    15. RIC-837 RMR is not forwarding messages from E2T to E2M
    16. RIC-835 → 2021-12-07 no news from Viktor
    17. fixed: RIC-971
  4. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
    6. 2023-02-14: No news yet, Thoralf received e-mail on this from James. Still to check.
    7. 2023-02-28: some e-mail discussion. Ball's on Bin Yang & James side. Subhash and Thoralf discussed this and Thoralf to call a meeting with Bin Yang, subhash, James, Thoralf.
    8. 2023-03-14: AP-James Meeting was held. We see use cases around deploying RIC platform using helm charts over O2; and deploying xApps over O2. For xApps the role of descriptor->helmcharts→k8s manifests in SMO is still missing. AP for James to check with SMO project on ASD (porting or making available "ricdms/dmscli" to SMO; kserve adapter also affected as it uses ricdms) and support for deploying using helm charts and James to discuss with RSAC. Bin-Yang wants to check how RIC can be deployed using helm charts only.
    9. 2023-03-28:no news
    10. 2023-04-11: Tacker team provided ideas on SMO architecture (in context of RSAC). No immediate action items for Near-RT RIC platform project
    11. 2023-04-25, 2023-05-09: no news
  5. Prashant's work in near-RT RIC
    1. 2023-04-25:
      1. Prashant updated call flow for A1 polciy status update. Will send it for review RIC-973.
      2. Prashant, pls. create JIRA item for the Golang implementation related to policytypes: RIC-975 → DONE
      3. Prashant, pls. create JIRA item for the SCTP E2 timeout change.  RIC-976 Three reviews, but only one is valid
    2. 2023-05-09
      1. question related to O1 (for stats handling without Vespa) - see RIC-798
  6. James: updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14, 2023-03-28 : no news
    3. 2023-04-11: H release test cases related O2 IMS committed into it/test. Some of these related to existing robot test cases.
    4. 2023-04-25: no updates
    5. 2023-05-09:
      1. Q-to-James: summary of what you presented in TOC (1 min) and let's raise question to all for input to integration project.
        1. Xtesting is used in integration project now (already for 6 months or so). Xtesting works also with robot test cases.
        2. James working in this integration for the test cases that are already in it/test. Infrastructure team also contributed O2 releated robot test cases (requires o-loud).
        3. Input from other subprojects, incl. our near-RT RIC project?
      2. James needs some hints on how to run the existing robot test cases in it/test related to missing env variables: GLOBAL_INJECTED_E2MGR_USER and APPMGR_ENDPOINT.
  7. Sunil updates?
    1. 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25: no news
    2. 2023-05-09 no news
  8. Subhash/Naman updates?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
        2. Integration with AI/ML project: kserve_adapter
          1. data pipeline (Hoejoo's e-mail)
            1. 2023-01-31 not discussed in today's meeting
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work
    3. 2023-03-28: work continues
    4. 2023-04-11: E2 reset work in submgr is now under work.
    5. 2023-04-25: Naman working on E2 reset (submgr part), ricdms not too much progress. no update on kserve
    6. 2023-05-09:
      1. E2 reset done, but still one more review coming on submgr to block subscriptions fo0r E2 nodes under reset.
      2. A1 bug fixes being almost ready.
      3. A1 mediator nanobot might be delayed.
      4. AI/ML adapter work is still ongoing - ricdms changes still coming during next 1-2 weeks.
  9. Abhijit updates?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14:now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
    3. 2023-03-28: working on RIC-969 and part of RIC-957
    4. 2023-04-11:
      1. RIC-969 first set of APIs (SDL) implemented. RNIB not yet (also under RIC-969).
      2. hw world xApp should grow with the implementation of xapp-frame-rust. Initial hw-rust xapp will show use of SDL/RNIB.
    5. 2023-04-25
      1. working on RNIB support in rust (https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10906) and next step hw-rust.
    6. 2023-05-09
      1. RIC-977 (subscription API) - pls. merge.
      2. RIC-978 pls. try to complete during this week.
      3. issues with E2 simulator → to get in contact with Naman and Subhash
  10. Cap Gemini updates? 
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
    2. 2023-03-28, 2023-04-11, 2023-04-25: no news.
    3. 2023-05-09 no news.
  11. Himanshu would like to work on RIC-963
    1. code changes, but difficult to test as difficult to change order of IEs in message.
  12. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  13. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25, 2023-05-09: no update
  14. RICAPP agenda: RICAPP Meetings.

2023-04-25

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2/+/10803 OK, bug fixed for dynamic log level change
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10675 OK, tests included
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27, 2022-11-22, 2023-03-28, 2023-04-11:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-972 URL for A1 mediator to align with spec.
    2. RIC-971 Fix potential segfaults and double free corruption (in E2T)
    3. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    4. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    5. RIC-915 dms_cli for installing xapp not working (raised by James)
    6. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    7. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    8. RIC-897 SCTP connection fails with Viavi // update with workaround
    9. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    10. RIC-894 long idle period (days) causes RMR connection breaks
    11. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    12. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    13. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    14. RIC-837 RMR is not forwarding messages from E2T to E2M
    15. RIC-835 → 2021-12-07 news from Viktor
    16. fixed:
  4. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
    6. 2023-02-14: No news yet, Thoralf received e-mail on this from James. Still to check.
    7. 2023-02-28: some e-mail discussion. Ball's on Bin Yang & James side. Subhash and Thoralf discussed this and Thoralf to call a meeting with Bin Yang, subhash, James, Thoralf.
    8. 2023-03-14: AP-James Meeting was held. We see use cases around deploying RIC platform using helm charts over O2; and deploying xApps over O2. For xApps the role of descriptor->helmcharts→k8s manifests in SMO is still missing. AP for James to check with SMO project on ASD (porting or making available "ricdms/dmscli" to SMO; kserve adapter also affected as it uses ricdms) and support for deploying using helm charts and James to discuss with RSAC. Bin-Yang wants to check how RIC can be deployed using helm charts only.
    9. 2023-03-28:no news
    10. 2023-04-11: Tacker team provided ideas on SMO architecture (in context of RSAC). No immediate action items for Near-RT RIC platform project
    11. 2023-04-25: we did not discuss
  5. Prashant's work in near-RT RIC
    1. 2023-04-25:
      1. Prashant updated call flow for A1. Will send it for review RIC-973
      2. Prashant, pls. create JIRA item for the Golang implementation related to policytypes: RIC-975
      3. Prashant, pls. create JIRA item for the SCTP E2 timeout change.  RIC-976
  6. James: updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14, 2023-03-28 : no news
    3. 2023-04-11: H release test cases related O2 IMS committed into it/test. Some of these related to existing robot test cases.
    4. 2023-04-25: no updates
  7. Sunil updates?
    1. 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25: no news
  8. Subhash/Naman updates?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
        2. Integration with AI/ML project: kserve_adapter
          1. data pipeline (Hoejoo's e-mail)
            1. 2023-01-31 not discussed in today's meeting
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work
    3. 2023-03-28: work continues
    4. 2023-04-11: E2 reset work in submgr is now under work.
    5. 2023-04-25: Naman working on E2 reset (submgr part), ricdms not too much progress. no update on kserve
  9. Abhijit updates?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14:now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
    3. 2023-03-28: working on RIC-969 and part of RIC-957
    4. 2023-04-11:
      1. RIC-969 first set of APIs (SDL) implemented. RNIB not yet (also under RIC-969).
      2. hw world xApp should grow with the implementation of xapp-frame-rust. Initial hw-rust xapp will show use of SDL/RNIB.
    5. 2023-04-25
      1. working on RNIB support in rust (https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10906) and next step hw-rust.
  10. Cap Gemini updates?
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
    2. 2023-03-28, 2023-04-11, 2023-04-25: no news.
  11. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  12. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14, 2023-03-28, 2023-04-11, 2023-04-25: no update
  13. Himanshu would like to work on RIC-963 → ok.
  14. Anybody ever tried RIC platform with IPv6? E2T should work with IPv6 for E2. Rest Thoralf does not know.
  15. RICAPP agenda: RICAPP Meetings.

2023-04-11

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-04-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2/+/10803 OK, bug fixed for dynamic log level change
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10675 OK, tests included
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27, 2022-11-22, 2023-03-28, 2023-04-11:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-972 URL for A1 mediator to align with spec.
    2. RIC-971 Fix potential segfaults and double free corruption (in E2T)
    3. RIC-965 RMR wormhole connections uses stale endpoints to make connections 
    4. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    5. RIC-915 dms_cli for installing xapp not working (raised by James)
    6. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    7. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    8. RIC-897 SCTP connection fails with Viavi // update with workaround
    9. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    10. RIC-894 long idle period (days) causes RMR connection breaks
    11. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    12. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    13. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    14. RIC-837 RMR is not forwarding messages from E2T to E2M
    15. RIC-835 → 2021-12-07 news from Viktor
    16. fixed: RIC-962, RIC-961, RIC-964, RIC-966, RIC-968, RIC-939, RIC-940. RIC-970
  4. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
    6. 2023-02-14: No news yet, Thoralf received e-mail on this from James. Still to check.
    7. 2023-02-28: some e-mail discussion. Ball's on Bin Yang & James side. Subhash and Thoralf discussed this and Thoralf to call a meeting with Bin Yang, subhash, James, Thoralf.
    8. 2023-03-14: AP-James Meeting was held. We see use cases around deploying RIC platform using helm charts over O2; and deploying xApps over O2. For xApps the role of descriptor->helmcharts→k8s manifests in SMO is still missing. AP for James to check with SMO project on ASD (porting or making available "ricdms/dmscli" to SMO; kserve adapter also affected as it uses ricdms) and support for deploying using helm charts and James to discuss with RSAC. Bin-Yang wants to check how RIC can be deployed using helm charts only.
    9. 2023-03-28:no news
    10. 2023-04-11: Tacker team provided ideas on SMO architecture (in context of RSAC). No immediate action items for Near-RT RIC platform project
  5. Prashant's work in near-RT RIC
    1. Example of additional work needed: A1 - registry and "policystatusobject" (defined in spec, but not implemented in OSC near-RT RIC)
      1. best approach is to create a JIRA item and attach document to it
      2. link to JIRA item
      3. Another issue was related to SCTP in E2. Prashant will write an e-mail on the topic (incl Alexandre )
    2. Naman/subhash commented that e-mail is maybe good enough.
  6. James:updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14, 2023-03-28 : no news
    3. 2023-04-11: H release test cases related O2 IMS committed into it/test. Some of these related to existing robot test cases.
  7. Sunil updates?
    1. 2023-03-14, 2023-03-28, 2023-04-11: no news
  8. Subhash/Naman updates?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
        2. Integration with AI/ML project: kserve_adapter
          1. data pipeline (Hoejoo's e-mail)
            1. 2023-01-31 not discussed in today's meeting
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work
    3. 2023-03-28: work continues
    4. 2023-04-11: E2 reset work in submgr is now under work.
  9. Abhijit updates?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14:now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
    3. 2023-03-28: working on RIC-969 and part of RIC-957
    4. 2023-04-11:
      1. RIC-969 first set of APIs (SDL) implemented. RNIB not yet (also under RIC-969).
      2. hw world xApp should grow with the implementation of xapp-frame-rust. Initial hw-rust xapp will show use of SDL/RNIB.
  10. Cap Gemini updates?
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
    2. 2023-03-28, 2023-04-11: no news.
  11. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  12. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14, 2023-03-28, 2023-04-11: no update
  13. RICAPP agenda: RICAPP Meetings.

2023-03-28 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-02-28
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/10666 OK
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/submgr/+/10287 OK
      3. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10405 how automated CI module testing can be done is to be discussed // also need to discuss CI // already known that this requires discussion with LF
        1. 2023-02-28: Abhijit worked with Matt and Sridhar from LF on this. Jobs are now running, but they fail. There's a credential issue. Abhijit to remind Sridhar. Once this is fixed, we can change Dockerfile to install prerequisites.
        2. 2023-03-28: This is OK and is now closed.
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27, 2022-11-22, 2023-03-28:  we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. new bug report RIC-962

    2. RIC-961 (fixed already)

    3. RIC-964 (fixed already)

    4. RIC_966 (fixed already)

    5. RIC-968 (fixed already)

    6. RIC-940 sdlpy missing whitespace → Timo
    7. RIC-939 race conditions in RMR → Abdulwahid
    8. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    9. RIC-915 dms_cli for installing xapp not working (raised by James)
    10. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    11. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    12. RIC-897 SCTP connection fails with Viavi // update with workaround
    13. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    14. RIC-894 long idle period (days) causes RMR connection breaks
    15. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    16. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    17. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    18. RIC-837 RMR is not forwarding messages from E2T to E2M
    19. RIC-835 → 2021-12-07 news from Viktor
    20. fixed: no new fixes
    21. anybody would like to get more familiar with RMR?
  4. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
    6. 2023-02-14 No news yet, Thoralf received e-mail on this from James. Still to check.
    7. 2023-02-28: some e-mail discussion. Ball's on Bin Yang & James side. Subhash and Thoralf discussed this and Thoralf to call a meeting with Bin Yang, subhash, James, Thoralf.
    8. 2023-03-14: AP-James Meeting was held. We see use cases around deploying RIC platform using helm charts over O2; and deploying xApps over O2. For xApps the role of descriptor->helmcharts→k8s manifests in SMO is still missing. AP for James to check with SMO project on ASD (porting or making available "ricdms/dmscli" to SMO; kserve adapter also affected as it uses ricdms) and support for deploying using helm charts and James to discuss with RSAC. Bin-Yang wants to check how RIC can be deployed using helm charts only.
    9. 2023-03-28: no news
  5. James:updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14, 2023-03-28: : no news
  6. Sunil updates?
    1. 2023-03-14, 2023-03-28: : no news
  7. Subhash/Naman updates?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
        2. Integration with AI/ML project: kserve_adapter
          1. data pipeline (Hoejoo's e-mail)
            1. 2023-01-31 not discussed in today's meeting
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work
    3. 2023-03-28: work continues
  8. Abhijit updates?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14:now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
    3. 2023-03-28: working on RIC-969 and part of RIC-957
  9. Cap Gemini updates?
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
    2. 2023-03-28: no news.
  10. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  11. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14, 2023-03-28 : no update
  12. RICAPP agenda: RICAPP Meetings.

2023-03-14 (Tuesday)

Recording: link to zoom recording

We stick to the 4pm Helsinki time slot for this meeting. Note that Europe will switch to summer time on March-26. So, for people not doing the switch at the same time, the meetings after March-26 start one hour earlier. Reminder for participants from the US: The US already switched to summer time on Mar-12.

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-02-28
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10405 how automated CI module testing can be done is to be discussed // also need to discuss CI // already known that this requires discussion with LF
        1. 2023-02-28: Abhijit worked with Matt and Sridhar from LF on this. Jobs are now running, but they fail. There's a credential issue. Abhijit to remind Sridhar. Once this is fixed, we can change Dockerfile to install prerequisites.
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/submgr/+/10287 → waiting for test cases, Gunja know and will update test case.
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-11-22we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. new bug report RIC-962

    2. RIC-961 (fixed already)

    3. RIC-964 (fixed already)

    4. RIC_966 (fixed already)

    5. RIC-968 (fixed already)

    6. RIC-940 sdlpy missing whitespace → Timo
    7. RIC-939 race conditions in RMR → Abdulwahid
    8. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    9. RIC-915 dms_cli for installing xapp not working (raised by James)
    10. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    11. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    12. RIC-897 SCTP connection fails with Viavi // update with workaround
    13. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    14. RIC-894 long idle period (days) causes RMR connection breaks
    15. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    16. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    17. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    18. RIC-837 RMR is not forwarding messages from E2T to E2M
    19. RIC-835 → 2021-12-07 news from Viktor
    20. fixed: no new fixes
    21. anybody would like to get more familiar with RMR?
  4. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
    6. 2023-02-14 No news yet, Thoralf received e-mail on this from James. Still to check.
    7. 2023-02-28: some e-mail discussion. Ball's on Bin Yang & James side. Subhash and Thoralf discussed this and Thoralf to call a meeting with Bin Yang, subhash, James, Thoralf.
    8. 2023-03-14: AP-James Meeting was held. We see use cases around deploying RIC platform using helm charts over O2; and deploying xApps over O2. For xApps the role of descriptor->helmcharts→k8s manifests in SMO is still missing. AP for James to check with SMO project on ASD (porting or making available "ricdms/dmscli" to SMO; kserve adapter also affected as it uses ricdms) and support for deploying using helm charts and James to discuss with RSAC. Bin-Yang wants to check how RIC can be deployed using helm charts only.
  5. James:updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-03-14: no news
  6. Sunil updates?
    1. 2023-03-14: no news
  7. Subhash/Naman updates?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
    2. 2023-03-14:
      1. E2 Reset E2mgr changes done. submgr change and notification to xapp still open.
      2. A1 mediator nanobot integration still under work.
  8. Abhijit updates?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
    2. 2023-03-14: now has access to hw-rust, but not yet xapp-frame-rust (no need to escalate yet). CI for xapp-frame-rust works now.
  9. Cap Gemini updates?
    1. 2023-03-14
      1. RIC-851 done
      2. RIC-967 (RIC subscription delete required related changes in xApp communication) added to H release. We discussed this in a meeting and decided to implement pre and post notifications aligned with RICARCH.
  10. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  11. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31, 2023-02-14, 2023-02-28, 2023-03-14: no update
  12. Integration with AI/ML project: kserve_adapter
    1. data pipeline (Hoejoo's e-mail)
      1. 2023-01-31 not discussed in today's meeting
  13. Gunja and Sachin (CapGemini) presented changes that were done for RIC subscription delete required as per RIC-851. Thoralf to start a mail thread with Nitin, Subhash, Gunja, Sachin on how xapps can be notified of subscription changes. link to the presentation 2023-03-14: Discussion done and resulted in RIC-967.
  14. RICAPP agenda: RICAPP Meetings.

2023-02-28 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on 2023-02-28
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/10405 how automated CI module testing can be done is to be discussed // also need to discuss CI // already known that this requires discussion with LF
        1. 2023-02-28: Abhijit worked with Matt and Sridhar from LF on this. Jobs are now running, but they fail. There's a credential issue. Abhijit to remind Sridhar. Once this is fixed, we can change Dockerfile to install prerequisites.
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/submgr/+/10287 → waiting for test cases, Gunja know and will update test case.
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-11-22we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-940 sdlpy missing whitespace → Timo
    2. RIC-939 race conditions in RMR → Abdulwahid
    3. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    4. RIC-915 dms_cli for installing xapp not working (raised by James)
    5. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    6. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    7. RIC-897 SCTP connection fails with Viavi // update with workaround
    8. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    9. RIC-894 long idle period (days) causes RMR connection breaks
    10. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    11. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    12. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    13. RIC-837 RMR is not forwarding messages from E2T to E2M
    14. RIC-835 → 2021-12-07 news from Viktor
    15. fixed: no new fixes
    16. anybody would like to get more familiar with RMR?
  4. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
    6. 2023-02-14 No news yet, Thoralf received e-mail on this from James. Still to check.
    7. 2023-02-28: some e-mail discussion. Ball's on Bin Yang & James side. Subhash and Thoralf discussed this and Thoralf to call a meeting with Bin Yang, subhash, James, Thoralf.
  5. James:updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-02-14: no updates
    3. 2023-02-28: no updates (James did not participate).
  6. Sunil updates?
    1. 2023-02-28: no updates
  7. Subhash/Naman updates?
    1. 2023-02-28: working on RNIB models for E2 reset. Nanobot integration with A1 mediator. kServe adapter work ongoing (RICDMS extension planned).
      1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
        1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
          1. Thoralf to create JIRA item for this
          2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
          3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
          4. https://wiki.o-ran-sc.org/plugins/servlet/mobile?contentId=67535114#content/view/67535114 
  8. Abhijit updates?
    1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      1. Thoralf raised support request to LF. Reminders sent. Still no solution.
  9. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  10. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31, 2023-02-14, 2023-02-28: no update
  11. Integration with AI/ML project: kserve_adapter
    1. data pipeline (Hoejoo's e-mail)
      1. 2023-01-31 not discussed in today's meeting
  12. Gunja and Sachin CapGemini) presented changes that were done for RIC subscription delete required as per RIC-851. Thoralf to start a mail thread with Nitin, Subhash, Gunja, Sachin on how xapps can be notified of subscription changes. link to the presentation
  13. RICAPP agenda: RICAPP Meetings.

2023-02-14 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on  Dec-15
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/9117 how automated CI module testing can be done is to be discussed // also need to discuss CI // already known that this requires discussion with LF
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-11-22we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-940 sdlpy missing whitespace → Timo
    2. RIC-939 race conditions in RMR → Abdulwahid
    3. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    4. RIC-915 dms_cli for installing xapp not working (raised by James)
    5. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    6. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    7. RIC-897 SCTP connection fails with Viavi // update with workaround
    8. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    9. RIC-894 long idle period (days) causes RMR connection breaks
    10. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    11. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    12. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    13. RIC-837 RMR is not forwarding messages from E2T to E2M
    14. RIC-835 → 2021-12-07 news from Viktor
    15. fixed: no new fixes
    16. anybody would like to get more familiar with RMR?
  4. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
    6. 2023-02-14 No news yet, Thoralf received e-mail on this from James. Still to check.
  5. Sunil still to discuss with other team members for other items from subteam-h
    1. 2023-02-14: Sunil provided list with four items.
  6. James:updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
    2. 2023-02-14: not updates
  7. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  8. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31: no update
    3. 2023-02-14: no update
  9. Johannes/Bryan: RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2023-01-31: Abhijit wanted to merge something. pls. contact Thoralf.
      1. no news from Johannes/Bryan
    2. 2023-02-14:
      1. Abhijit is now committer for the rust subsystems (platform and xapp) - but there seem to be issues on LF side that didn't actually made this happen.
      2. Thoralf to raise support request to LF
  10. Integration with AI/ML project: kserve_adapter
    1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
      1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
        1. Thoralf to create JIRA item for this
        2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. But also ok if only in one.
        3. 2023-02-14: Subhash discussed with Hoejoo on this (internally) - maybe a presentation coming later
    2. data pipeline (Hoejoo's e-mail)
      1. 2023-01-31 not discussed in today's meeting
  11. CapGemini to present to project meeting changes that were done for RIC subscription delete required
  12. RICAPP agenda: RICAPP Meetings.


2023-01-31 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on  Dec-15
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/9117 how automated CI module testing can be done is to be discussed // also need to discuss CI // already known that this requires discussion with LF
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-11-22we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-940 sdlpy missing whitespace → Timo
    2. RIC-939 race conditions in RMR → Abdulwahid
    3. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    4. RIC-915 dms_cli for installing xapp not working (raised by James)
    5. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    6. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    7. RIC-897 SCTP connection fails with Viavi // update with workaround
    8. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    9. RIC-894 long idle period (days) causes RMR connection breaks
    10. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    11. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    12. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    13. RIC-837 RMR is not forwarding messages from E2T to E2M
    14. RIC-835 → 2021-12-07 news from Viktor
    15. fixed: no new fixes
    16. anybody would like to get more familiar with RMR?
  4. Mark your affiliation in https://openprofile.dev  so that statistics are correctly generated.
  5. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Could be implemented as second option for deploying xApps.
    5. 2023-01-31: No news yet
  6. Sunil still to discuss with other team members for other items from subteam-h
    1. 2023-01-31: no news yet. HCL still in internal discussion on what open-src items to work on in 1H2023
  7. James:updates?
    1. 2023-01-31:
      1. working on existing robot test cases (that integrate xapps and platform) to be part of xtesting tests.
      2. Subhash asked for a wiki page documenting this work.
      3. WR also want to contribute to xtesting for O2. CNF package definition still open and concept of DMS.
        1. discussion with Bin Yang in this meeting is possible. Maybe some proposal would be good.
        2. Tacker-based deployment needs to be checked.
  8. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. We go through the rough views on what you might want to work on. Also as input use delayed items from previous release link
  9. GRPC vs RMR
    1. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
    2. 2023-01-31: no update
  10. Johannes/Bryan: RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2023-01-31: Abhijit wanted to merge something. pls. contact Thoralf.
      1. no news from Johannes/Bryan
  11. Integration with AI/ML project: kserve_adapter
    1. Kserve adapter (mentioned in RSAC and e-mail from Hoejoo),
      1. 2023-01-31 Joseph presented the kserve part. We agreed as working assumption to go for solution #1 (slide 2) with model-based inference. Comments by e-mail to Joseph. Slideset: link
        1. Thoralf to create JIRA item for this
        2. Subhash/Thoralf commented that ricdms cli and REST should be implemented at same time. BUt also ok if only in one.
    2. data pipeline (Hoejoo's e-mail)
      1. 2023-01-31 not discussed in today's meeting
  12. RICAPP agenda: RICAPP Meetings.


2023-01-17 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. Last checked on  Dec-15
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/9117 how automated CI module testing can be done is to be discussed // also need to discuss CI // already known that this requires discussion with LF
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-11-22we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-940 sdlpy missing whitespace → Timo
    2. RIC-939 race conditions in RMR → Abdulwahid
    3. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    4. RIC-915 dms_cli for installing xapp not working (raised by James)
    5. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    6. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    7. RIC-897 SCTP connection fails with Viavi // update with workaround
    8. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    9. RIC-894 long idle period (days) causes RMR connection breaks
    10. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    11. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    12. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    13. RIC-837 RMR is not forwarding messages from E2T to E2M
    14. RIC-835 → 2021-12-07 news from Viktor
    15. fixed: no new fixes
    16. anybody would like to get more familiar with RMR?
  4. 2022-12-13, 2023-01-17: Bin Yang asked about O2 for RIC platform deployment and xapp deployment. Need to discuss on this topic. O-cloud is deployed in AT&T and Taiwan lab.

    1. The current platform deployment scripts might not be in line with O2 envisions
    2. David Liu (WR) asked from James on O2 as well. James to check if a proposal on using X testing framework could also be used for integration. There's is also a link to robot test cases.
    3. O2-D(MS) is relevant to RIC platform.
    4. deploying xApps (LCM) is also an O2 issue - the alternative of using CRDs is not implemented in OSC RIC. Coudl be implemented as second option for deploying xApps.
  5. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. RIC-860 + RIC-878
        1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
        2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
        3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
        4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
        5. 2022-04-26: still open
        6. 2022-05-11: expecting to finalize by May-27
        7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
        8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
        9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
        10. 2022-08-02: SUNIL SINGH to check any news on RIC-860 or RIC-878?
        11. 2022-08-16→2022-08-30->2022-09-13→2022-09-27: no update
        12. : some cleanup is needed first.
          1. RIC-860 - suggestion is to merge the one abandoned RIC-860 review and the one that is still open into one review and keep that as new review.
          2. RIC-878 - suggest to re-start review 8500 and merge it with the current open one for RIC-878 and start this as new review.
          3. test both if they are actually working
          4. 2022-08-30: team currently busy, but will pick up on this again soon
        13. 2023-01-17: for now remove form agenda and take back if we find someone to work on it.
      2. RIC-641 + RIC-705
        1. RIC-641: done in G
        2. RIC-705: xapp registration still open (for H?) → manage this via H content and don't keep it in the agenda.
  6. contributions by new contributor on asn.1 encoders/decoders and APER ASN.1↔XML tool - waiting for repo proposal
    1. created on 2022-08-30: Update 2022-09-13 → 2022-09-27: Now hanging with Augu. - waiting for reply
    2. 2023-01-17: no news → we drop this item from the agenda
  7. James:
    1. 2022-11-08: continues work with keysight (using KPI-mon-go xApp (E2APv1, and older E2SM). hw-go could be used if E2AP2.0 is needed. hw-go does not parse E2SM-parts.
      1. HCL also working on E2APv2.0 xApps.
    2. 2023-01-17: work with keysight completed before thanksgiving weekend (excl. xapp; focus on base E2AP cases). No need to keep this in the agenda.
  8. H release content
    1. we mark items that you are >90% sure (=”committed”) to work on during 1H2023 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for H release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint H release dev sprint 1: Feb-20´to Mar-12
      2. Sprint H release dev sprint 2: Mar-13 to Apr-2
      3. Sprint H release dev sprint 3: Apr-3 to Apr-23
      4. Sprint H release dev sprint 4: Apr-24 to May-14 (last planned development sprint)
      5. Sprint H release dev sprint 5: May-15 to Jun-4 (only for unplanned last-minute development items)
    3. Please prepare for next meeting a rough view on what you might want to work on. Also as input use delayed items from previous release link
  9. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
    6. Thoralf to schedule a meeting once a proposal is ready.
    7. 2022-08-16 →2022-08-30 → 2022-09-27 → 2022-10-11: no news yet, current approach we assume E2M manages E2 node to gNB list mapping and submgr (together with E2T) manage subscriptions. xApps to be aware of many E2T instances and many xApp instances.
    8. 2022-11-08: focus of Nokia proposal will be on scalability (xApps, #E2 connections)
    9. 2022-11-22: WG3 spec for RICAPI available in current train. Worth reading. Defines GRPC, but also SCTP+Protobuf interfaces.
    10. 2023-01-17: Still working this within Nokia. WG3 also discusses this.
  10. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2023-01-17: not discussed today.
  11. RICAPP agenda: RICAPP Meetings.
  12. Remember to click on "end meeting for all"


2023-01-03 (Tuesday)

Recording: Link to zoom recording

Sunil kindly agreed to host also the RIC platform part of this week's project meeting.

We will discuss the plans for the H release in the next meeting. As before, items that were delayed from the previous release and leftover items are prime candidates to work on. Left overs: link

2022-12-06 (Tuesday)

Recording:  Link to zoom recording

The meeting was hosted by Sunil.

Updates on RICP.

  1. Updates (from Subhash)
    1. RIC-385: first part done defining the E2 messages in golang, but actual Reset implementation still needed.  Rest goes to release H
    2. RIC-714: dms Rest interface. Instructions still missing
    3. RIC-914+RIC-849: done (helm charts and jenkins job still coming)
    4. RIC-911: done
  2. Updates (from Sunil)
    1. RIC-860 and RIC-878 code for REST subscriptiopn API is now actively being worked on.
  3. Updates (from Johannes)
    1. still struggling with CI, but likely to "formally" release RMR part of RUST framework.
  4. RICAPP agenda: RICAPP Meetings.

2022-11-22 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. 2022-10-11+2022-11-08+2022-11-22
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/9117 how automated CI module testing can be done is to be discussed // also need to discuss CI // already known that this requires discussion with LF
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-11-22we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-940 sdlpy missing whitespace → Timo
    2. RIC-939 race conditions in RMR → Abdulwahid
    3. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    4. RIC-915 dms_cli for installing xapp not working (raised by James)
    5. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    6. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    7. RIC-897 SCTP connection fails with Viavi // update with workaround
    8. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    9. RIC-894 long idle period (days) causes RMR connection breaks
    10. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    11. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    12. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    13. RIC-837 RMR is not forwarding messages from E2T to E2M
    14. RIC-835 → 2021-12-07 news from Viktor
    15. fixed: no new fixes
    16. anybody would like to get more familiar with RMR?
  4. demo day? Suggestion: Dec-20. Add demo topic here: 2022-12-20 Release G

  5. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. RIC-860 + RIC-878
        1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
        2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
        3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
        4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
        5. 2022-04-26: still open
        6. 2022-05-11: expecting to finalize by May-27
        7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
        8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
        9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
        10. 2022-08-02: SUNIL SINGH to check any news on RIC-860 or RIC-878?
        11. 2022-08-16→2022-08-30->2022-09-13→2022-09-27: no update
        12. : some cleanup is needed first.
          1. RIC-860 - suggestion is to merge the one abandoned RIC-860 review and the one that is still open into one review and keep that as new review.
          2. RIC-878 - suggest to re-start review 8500 and merge it with the current open one for RIC-878 and start this as new review.
          3. test both if they are actually working
          4. 2022-08-30: team currently busy, but will pick up on this again soon
      2. contributions by new contributor on asn.1 encoders/decoders and APER ASN.1↔XML tool - waiting for repo proposal
        1. created on 2022-08-30: Update 2022-09-13 → 2022-09-27: Now hanging with Augu. - waiting for reply
      3. RIC-641 Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
        1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
        2. 2022-06-21
          1. RIC-642 (python) done
          2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
        3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-cpp) out of the F release. Which means they are likely early G release features.
        4. 2022-07-19: RIC-912 for clean up of the build process (should use dockerfile). But we first try to get current review through
        5. 2022-08-02: SUNIL SINGH check status with Anh Nguyen
        6. 2022-08-16: any news?
          1. one optinion is to cleanup CI first with the approach in RIC-912
          2. there are also instructions for testing CI given by LF infra. Thoralf-to dig out the instructions
        7. 2022-08-30  Waiting for Anh Nguyen to come fully back to work.
        8. 2022-09-13→ 2022-09-27: no update, but Anh Nguyen is now back and in discussion with Anssi
        9. 2022-10-11: Anh Nguyen to pick up again. Thoralf fixed CI issues via sandbox, minor change in CI job definition and it commit.
  6. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: XTesting (used by Anuket) proposed as alternative to OTF (lack of support from OTF developers)
    5. 2022-07-19: James is working on it with LF
    6. 2022-08-02: any updates?
      1. caur.us (johannes@ c...) working on docker compose deployment (no K8S). usable in CI?
      2. James working Sridhar on xTesting.
    7. 2022-08-16 no news. Friday James will have further discussion with xTesting "evangelist" from Anuket
    8. 2022-08-30 progress on xTesting - first results to be presented in RSAC on Sep-21.
    9. 2022-09-13: kubectl version used in testing doesn't match expectations. Work in progress
    10. 2022-09-27: Demo is in the RSAC meeting from last week. Instructions are here: Automated Testing via XTesting And also watch the RSAC video recording from last week: link (fast forward to minute 9:00).
      1. next step: promote this to all OSC subprojects via TOC.
      2. James trying to run robot test cases in it/test.
    11. 2022-10-11: still work in progress. Second demonstration with updated scripts: https://wiki.o-ran-sc.org/download/attachments/3604609/XTesting-demo.mp4?api=v2
    12. 2022-11-08: continues work with keysight (using KPI-mon-go xApp (E2APv1, and older E2SM). hw-go could be used if E2AP2.0 is needed. hw-go does not parse E2SM-parts.
      1. HCL also working on E2APv2.0 xApps.
  7. G release content wrap up
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2022 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for G release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint G release dev sprint 1: Aug-22 to Sep-11
      2. Sprint G release dev sprint 2: Sep-12 to Oct-2
      3. Sprint G release dev sprint 3: Oct-3 to Oct-23
      4. Sprint G release dev sprint 4: Oct-24 to Nov-13 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-14 to Dec-4 (only for unplanned last-minute development items)
    3. link to G Release summary. Try to finalize all work by Dec-6 so we can generate the release images in the week of Dec-6

  8. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
    6. Thoralf to schedule a meeting once a proposal is ready.
    7. 2022-08-16 →2022-08-30 → 2022-09-27 → 2022-10-11: no news yet, current approach we assume E2M manages E2 node to gNB list mapping and submgr (together with E2T) manage subscriptions. xApps to be aware of many E2T instances and many xApp instances.
    8. 2022-11-08: focus of Nokia proposal will be on scalability (xApps, #E2 connections)
    9. 2022-11-22: WG3 spec for RICAPI available in current train. Worth reading. Defines GRPC, but also SCTP+Protobuf interfaces.
  9. In O-RAN f-2-f in October, OSC has a three hour slot for presentations about what OSC did. RSAC coordinates this. Slideset on content of E and F release, show existing demo on RIC deploy, xapp deploy and connect simulator, show demo on E2AP2.0 incl. E2 config update (all together 30 min).
    1. 2022-09-13: likely the way we go forward - Subhash and Thoralf will handle
      1. 2022-09-27: Thoralf to create presentation material and send to subhash
      2. 2022-10-11: Material shared and sent to RSAC
      3. 2022-11-08: DONE
    2. FYI: FYUZ (O-RAN, TIP, Metaverse summit) happens the week after the O-RAN F-2-F (same place) - Thoralf will present on the O-RAN day
      1. 2022-11-08: DONE
      2. Thoralf talked about the RIC in the presentation "Panel 3 - The RIC: How to over-deliver on the promise". The panel 3 recording starts at 1:46:00 into the youtube video: https://youtu.be/W1i6EPQ1wzo?t=6370 Thoralf also talked in the breakout panel discussion "Unpacking the intelligence of RIC: optimization and automation of complexity" (no video)
      3. James organized a video loop for the OSC video recordings and James (CMCC) and and Ramesh (HCL) talked in the breakout panel discussion "Accelerating O-RAN adoption through open source"
      4. OAI planning to support E2SM-KPM/E2SM-RC in CU/DU/gNB
      5. ns-3 E2 adapter (GPL) is now published in OSC.
  10. Update from Samsung side
    1. news discussed in G release content section
  11. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-08-02
      1. hw-rust creation review by Johannes = https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70416 ?
      2. Sunil to contact Johannes that he abandons his change and we continue with Sunil's: https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70429
    2. 2022-09-13: working is progressing. end of September first commits should come.
    3. 2022-09-27: first commit likely coming this week. Johannes could demo in two weeks from now.
    4. 2022-10-11: first commit under review.
      1. 2022-10-11 Johannes to look into CI (and module tests) for Rust
        1. status: basic framework ready (ping-pong dmeo works between two xapps). next step SDL.
      2. 2022-11-08 demo (5-10min)
    5. 2022-11-22. Thoralf to ask for status
  12. RICAPP agenda: RICAPP Meetings.

2022-11-08 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. 2022-10-11+2022-11-08
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/9117 how automatec CI module testing can be done is to be discussed // also need to discuss CI // already known that this requires discussion with LF
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-11-08we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-940 sdlpy missing whitespace → Timo
    2. RIC-939 race conditions in RMR → Abdulwahid
    3. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    4. RIC-915 dms_cli for installing xapp not working (raised by James)
    5. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    6. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    7. RIC-897 SCTP connection fails with Viavi // update with workaround
    8. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    9. RIC-894 long idle period (days) causes RMR connection breaks
    10. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    11. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    12. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    13. RIC-837 RMR is not forwarding messages from E2T to E2M
    14. RIC-835 → 2021-12-07 news from Viktor
    15. fixed: RIC-943 (alarm-go), RIC-944 + RIC-945 (E2term)
    16. anybody would like to get more familiar with RMR?
  4. Suggestion: for the next meeting, as over the last two years, let's stick to the EET 4pm time slot even as the US and most parts of Europe change back from DST.

  5. demo day? Suggestion: Dec-20

  6. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. RIC-860 + RIC-878
        1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
        2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
        3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
        4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
        5. 2022-04-26: still open
        6. 2022-05-11: expecting to finalize by May-27
        7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
        8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
        9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
        10. 2022-08-02: SUNIL SINGH to check any news on RIC-860 or RIC-878?
        11. 2022-08-16→2022-08-30->2022-09-13→2022-09-27: no update
        12. : some cleanup is needed first.
          1. RIC-860 - suggestion is to merge the one abandoned RIC-860 review and the one that is still open into one review and keep that as new review.
          2. RIC-878 - suggest to re-start review 8500 and merge it with the current open one for RIC-878 and start this as new review.
          3. test both if they are actually working
          4. 2022-08-30: team currently busy, but will pick up on this again soon
      2. contributions by new contributor on asn.1 encoders/decoders and APER ASN.1↔XML tool - waiting for repo proposal
        1. created on 2022-08-30: Update 2022-09-13 → 2022-09-27: Now hanging with Augu. - waiting for reply
      3. RIC-641 Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
        1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
        2. 2022-06-21
          1. RIC-642 (python) done
          2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
        3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-cpp) out of the F release. Which means they are likely early G release features.
        4. 2022-07-19: RIC-912 for clean up of the build process (should use dockerfile). But we first try to get current review through
        5. 2022-08-02: SUNIL SINGH check status with Anh Nguyen
        6. 2022-08-16: any news?
          1. one optinion is to cleanup CI first with the approach in RIC-912
          2. there are also instructions for testing CI given by LF infra. Thoralf-to dig out the instructions
        7. 2022-08-30  Waiting for Anh Nguyen to come fully back to work.
        8. 2022-09-13→ 2022-09-27: no update, but Anh Nguyen is now back and in discussion with Anssi
        9. 2022-10-11: Anh Nguyen to pick up again. Thoralf fixed CI issues via sandbox, minor change in CI job definition and it commit.
  7. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: XTesting (used by Anuket) proposed as alternative to OTF (lack of support from OTF developers)
    5. 2022-07-19: James is working on it with LF
    6. 2022-08-02: any updates?
      1. caur.us (johannes@ c...) working on docker compose deployment (no K8S). usable in CI?
      2. James working Sridhar on xTesting.
    7. 2022-08-16 no news. Friday James will have further discussion with xTesting "evangelist" from Anuket
    8. 2022-08-30 progress on xTesting - first results to be presented in RSAC on Sep-21.
    9. 2022-09-13: kubectl version used in testing doesn't match expectations. Work in progress
    10. 2022-09-27: Demo is in the RSAC meeting from last week. Instructions are here: Automated Testing via XTesting And also watch the RSAC video recording from last week: link (fast forward to minute 9:00).
      1. next step: promote this to all OSC subprojects via TOC.
      2. James trying to run robot test cases in it/test.
    11. 2022-10-11: still work in progress. Second demonstration with updated scripts: https://wiki.o-ran-sc.org/download/attachments/3604609/XTesting-demo.mp4?api=v2
    12. 2022-11-08: continues work with keysight (using KPI-mon-go xApp (E2APv1, and older E2SM). hw-go could be used if E2AP2.0 is needed. hw-go does not parse E2SM-parts.
      1. HCL also working on E2APv2.0 xApps.
  8. G release content planning
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2022 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for G release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint G release dev sprint 1: Aug-22 to Sep-11
      2. Sprint G release dev sprint 2: Sep-12 to Oct-2
      3. Sprint G release dev sprint 3: Oct-3 to Oct-23
      4. Sprint G release dev sprint 4: Oct-24 to Nov-13 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-14 to Dec-4 (only for unplanned last-minute development items)
  9. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
    6. Thoralf to schedule a meeting once a proposal is ready.
    7. 2022-08-16 →2022-08-30 → 2022-09-27 → 2022-10-11: no news yet, current approach we assume E2M manages E2 node to gNB list mapping and submgr (together with E2T) manage subscriptions. xApps to be aware of many E2T instances and many xApp instances.
    8. 2022-11-08: focus of Nokia proposal will be on scalability (xApps, #E2 connections)
  10. In O-RAN f-2-f in October, OSC has a three hour slot for presentations about what OSC did. RSAC coordinates this. Slideset on content of E and F release, show existing demo on RIC deploy, xapp deploy and connect simulator, show demo on E2AP2.0 incl. E2 config update (all together 30 min).
    1. 2022-09-13: likely the way we go forward - Subhash and Thoralf will handle
      1. 2022-09-27: Thoralf to create presentation material and send to subhash
      2. 2022-10-11: Material shared and sent to RSAC
      3. 2022-11-08: DONE
    2. FYI: FYUZ (O-RAN, TIP, Metaverse summit) happens the week after the O-RAN F-2-F (same place) - Thoralf will present on the O-RAN day
      1. 2022-11-08: DONE
      2. Thoralf talked about the RIC in the presentation "Panel 3 - The RIC: How to over-deliver on the promise". The panel 3 recording starts at 1:46:00 into the youtube video: https://youtu.be/W1i6EPQ1wzo?t=6370 Thoralf also talked in the breakout panel discussion "Unpacking the intelligence of RIC: optimization and automation of complexity" (no video)
      3. James organized a video loop for the OSC video recordings and James (CMCC) and and Ramesh (HCL) talked in the breakout panel discussion "Accelerating O-RAN adoption through open source"
      4. OAI planning to support E2SM-KPM/E2SM-RC in CU/DU/gNB
      5. ns-3 E2 adapter (GPL) is now published in OSC.
  11. Update from Samsung side
    1. A1 - golang - Naman used RMR from E2 manager (not from xapp-framework).
    2. DMS REST server - Remote-API-equivalent to dmscli.
  12. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-08-02
      1. hw-rust creation review by Johannes = https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70416 ?
      2. Sunil to contact Johannes that he abandons his change and we continue with Sunil's: https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70429
    2. 2022-09-13: working is progressing. end of September first commits should come.
    3. 2022-09-27: first commit likely coming this week. Johannes could demo in two weeks from now.
    4. 2022-10-11: first commit under review.
      1. 2022-10-11 Johannes to look into CI (and module tests) for Rust
        1. status: basic framework ready (ping-pong dmeo works between two xapps). next step SDL.
      2. 2022-11-08 demo (5-10min)
  13. RICAPP agenda: RICAPP Meetings.

2022-10-25 (Tuesday)

CANCELLED due to conference participation and sick leave.

2022-10-11 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. 2022-10-11
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-rust/+/9117 how module testing can be done is to be discussed // also need to discuss CI
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-10-11we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-940 sdlpy missing whitespace → Timo
    2. RIC-939 race conditions in RMR → Abdulwahid
    3. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    4. RIC-915 dms_cli for installing xapp not working (raised by James)
    5. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    6. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    7. RIC-897 SCTP connection fails with Viavi // update with workaround
    8. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    9. RIC-894 long idle period (days) causes RMR connection breaks
    10. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    11. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    12. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    13. RIC-837 RMR is not forwarding messages from E2T to E2M
    14. RIC-835 → 2021-12-07 news from Viktor
    15. fixed: no new fixes.
    16. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. RIC-860 + RIC-878
        1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
        2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
        3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
        4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
        5. 2022-04-26: still open
        6. 2022-05-11: expecting to finalize by May-27
        7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
        8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
        9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
        10. 2022-08-02: SUNIL SINGH to check any news on RIC-860 or RIC-878?
        11. 2022-08-16→2022-08-30->2022-09-13→2022-09-27: no update
        12. : some cleanup is needed first.
          1. RIC-860 - suggestion is to merge the one abandoned RIC-860 review and the one that is still open into one review and keep that as new review.
          2. RIC-878 - suggest to re-start review 8500 and merge it with the current open one for RIC-878 and start this as new review.
          3. test both if they are actually working
          4. 2022-08-30: team currently busy, but will pick up on this again soon
      2. contributions by new contributor on asn.1 encoders/decoders and APER ASN.1↔XML tool - waiting for repo proposal
        1. created on 2022-08-30: Update 2022-09-13 → 2022-09-27: Now hanging with Augu. - waiting for reply
      3. RIC-641 Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
        1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
        2. 2022-06-21
          1. RIC-642 (python) done
          2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
        3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-cpp) out of the F release. Which means they are likely early G release features.
        4. 2022-07-19: RIC-912 for clean up of the build process (should use dockerfile). But we first try to get current review through
        5. 2022-08-02: SUNIL SINGH check status with Anh Nguyen
        6. 2022-08-16: any news?
          1. one optinion is to cleanup CI first with the approach in RIC-912
          2. there are also instructions for testing CI given by LF infra. Thoralf-to dig out the instructions
        7. 2022-08-30  Waiting for Anh Nguyen to come fully back to work.
        8. 2022-09-13→ 2022-09-27: no update, but Anh Nguyen is now back and in discussion with Anssi
        9. 2022-10-11: Anh Nguyen to pick up again. Thoralf fixed CI issues via sandbox, minor change in CI job definition and it commit.
  5. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: XTesting (used by Anuket) proposed as alternative to OTF (lack of support from OTF developers)
    5. 2022-07-19: James is working on it with LF
    6. 2022-08-02: any updates?
      1. caur.us (johannes@ c...) working on docker compose deployment (no K8S). usable in CI?
      2. James working Sridhar on xTesting.
    7. 2022-08-16 no news. Friday James will have further discussion with xTesting "evangelist" from Anuket
    8. 2022-08-30 progress on xTesting - first results to be presented in RSAC on Sep-21.
    9. 2022-09-13: kubectl version used in testing doesn't match expectations. Work in progress
    10. 2022-09-27: Demo is in the RSAC meeting from last week. Instructions are here: Automated Testing via XTesting And also watch the RSAC video recording from last week: link (fast forward to minute 9:00).
      1. next step: promote this to all OSC subprojects via TOC.
      2. James trying to run robot test cases in it/test.
    11. 2022-10-11: still work in progress. Second demonstration with updated scripts: https://wiki.o-ran-sc.org/download/attachments/3604609/XTesting-demo.mp4?api=v2
  6. 2022-10-11: last remaining demo from F-release
    1. 10min RIC-642 xapp-frame-py subscription REST interface → end of August → middle of Sept → (updated 2022-09-27): now scheduled for 2022-10-11 (Erkki)
  7. G release content planning
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2022 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for G release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint G release dev sprint 1: Aug-22 to Sep-11
      2. Sprint G release dev sprint 2: Sep-12 to Oct-2
      3. Sprint G release dev sprint 3: Oct-3 to Oct-23
      4. Sprint G release dev sprint 4: Oct-24 to Nov-13 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-14 to Dec-4 (only for unplanned last-minute development items)
  8. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
    6. Thoralf to schedule a meeting once a proposal is ready.
    7. 2022-08-16 →2022-08-30 → 2022-09-27 → 2022-10-11: no news yet, current approach we assume E2M manages E2 node to gNB list mapping and submgr (together with E2T) manage subscriptions. xApps to be aware of many E2T instances and many xApp instances.
  9. In O-RAN f-2-f in October, OSC has a three hour slot for presentations about what OSC did. RSAC coordinates this. Slideset on content of E and F release, show existing demo on RIC deploy, xapp deploy and connect simulator, show demo on E2AP2.0 incl. E2 config update (all together 30 min).
    1. 2022-09-13: likely the way we go forward - Subhash and Thoralf will handle
      1. 2022-09-27: Thoralf to create presentation material and send to subhash
      2. 2022-10-11: Material shared and sent to RSAC
    2. FYI: FYUZ (O-RAN, TIP, Metaverse summit) happens the week after the O-RAN F-2-F (same place) - Thoralf will present on the O-RAN day
  10. Update from Samsung side
    1. A1 - golang - Naman used RMR from E2 manager (not from xapp-framework). Need module label - Thoralf to check. Add Alexandre to mail chain.
    2. DMS REST server - Remote-API-equivalent to dmscli. Abukar + Abdulwahid-team and Samsung team on reviewing DMS server implementation. TODO-Thoralf
  11. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-08-02
      1. hw-rust creation review by Johannes = https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70416 ?
      2. Sunil to contact Johannes that he abandons his change and we continue with Sunil's: https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70429
    2. 2022-09-13: working is progressing. end of September first commits should come.
    3. 2022-09-27: first commit likely coming this week. Johannes could demo in two weeks from now.
    4. 2022-10-11: first commit under review.
      1. 2022-10-11 Johannes to look into CI (and module tests) for Rust
        1. status: basic framework ready (ping-pong dmeo works between two xapps). next step SDL.
      2. 2022-10-25 demo
  12. host for 2022-10-25? - Sunil
  13. RICAPP agenda: RICAPP Meetings.

2022-09-27 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. 2022-09-27
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/9006https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/9020 OK, (influx update) only deployment changes. So ok with test case.
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/stslgo/+/9010https://gerrit.o-ran-sc.org/r/c/ric-plt/stslgo/+/9047 OK, (influx update) test cases included.
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-08-30, 2022-09-13, 2022-09-27we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. 2022-09-27: one new bug: RIC-940 → Timo
    2. RIC-940 sdlpy missing whitespace → Timo
    3. RIC-939 race conditions in RMR → Abdulwahid
    4. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    5. RIC-915 dms_cli for installing xapp not working (raised by James)
    6. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    7. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    8. RIC-897 SCTP connection fails with Viavi // update with workaround
    9. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    10. RIC-894 long idle period (days) causes RMR connection breaks
    11. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    12. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    13. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    14. RIC-837 RMR is not forwarding messages from E2T to E2M
    15. RIC-835 → 2021-12-07 news from Viktor
    16. fixed: no new fixes.
    17. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. RIC-860 + RIC-878
        1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
        2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
        3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
        4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
        5. 2022-04-26: still open
        6. 2022-05-11: expecting to finalize by May-27
        7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
        8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
        9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
        10. 2022-08-02: SUNIL SINGH to check any news on RIC-860 or RIC-878?
        11. 2022-08-16→2022-08-30->2022-09-13→2022-09-27: no update
        12. : some cleanup is needed first.
          1. RIC-860 - suggestion is to merge the one abandoned RIC-860 review and the one that is still open into one review and keep that as new review.
          2. RIC-878 - suggest to re-start review 8500 and merge it with the current open one for RIC-878 and start this as new review.
          3. test both if they are actually working
          4. 2022-08-30: team currently busy, but will pick up on this again soon
      2. contributions by new contributor on asn.1 encoders/decoders and APER ASN.1↔XML tool - waiting for repo proposal
        1. created on 2022-08-30: Update 2022-09-13 → 2022-09-27: Now hanging with Augu. - waiting for reply
      3. RIC-641 Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
        1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
        2. 2022-06-21
          1. RIC-642 (python) done
          2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
        3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-cpp) out of the F release. Which means they are likely early G release features.
        4. 2022-07-19: RIC-912 for clean up of the build process (should use dockerfile). But we first try to get current review through
        5. 2022-08-02: SUNIL SINGH check status with Anh Nguyen
        6. 2022-08-16: any news?
          1. one optinion is to cleanup CI first with the approach in RIC-912
          2. there are also instructions for testing CI given by LF infra. Thoralf-to dig out the instructions
        7. 2022-08-30  Waiting for Anh Nguyen to come fully back to work.
        8. 2022-09-13→ 2022-09-27: no update, but Anh Nguyen is now back and in discussion with Anssi
  5. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: XTesting (used by Anuket) proposed as alternative to OTF (lack of support from OTF developers)
    5. 2022-07-19: James is working on it with LF
    6. 2022-08-02: any updates?
      1. caur.us (johannes@ c...) working on docker compose deployment (no K8S). usable in CI?
      2. James working Sridhar on xTesting.
    7. 2022-08-16 no news. Friday James will have further discussion with xTesting "evangelist" from Anuket
    8. 2022-08-30 progress on xTesting - first results to be presented in RSAC on Sep-21.
    9. 2022-09-13: kubectl version used in testing doesn't match expectations. Work in progress
    10. 2022-09-27: Demo is in the RSAC meeting from last week. Instructions are here: Automated Testing via XTesting And also watch the RSAC video recording from last week. TODO
      1. next step: promote this to all OSC subprojects via TOC.
      2. James trying to run robot test cases in it/test.
  6. 2022-07-05: still one remaining demos.
    1. 10min RIC-642 xapp-frame-py subscription REST interface → end of August → middle of Sept → (updated 2022-09-27): now scheduled for 2022-10-11 (Erkki)
  7. G release content planning
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2022 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for G release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint G release dev sprint 1: Aug-22 to Sep-11
      2. Sprint G release dev sprint 2: Sep-12 to Oct-2
      3. Sprint G release dev sprint 3: Oct-3 to Oct-23
      4. Sprint G release dev sprint 4: Oct-24 to Nov-13 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-14 to Dec-4 (only for unplanned last-minute development items)
  8. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
    6. Thoralf to schedule a meeting once a proposal is ready.
    7. 2022-08-16 →2022-08-30 → 2022-09-27: no news yet, current approach we assume E2M manages E2 node to gNB list mapping and submgr (together with E2T) manage subscriptions. xApps to be aware of many E2T instances and many xApp instances.
  9. In O-RAN f-2-f in October, OSC has a three hour slot for presentations about what OSC did. RSAC coordinates this. Slideset on content of E and F release, show existing demo on RIC deploy, xapp deploy and connect simulator, show demo on E2AP2.0 incl. E2 config update (all together 30 min).
    1. 2022-09-13: likely the way we go forward - Subhash and Thoralf will handle
    2. FYI: FYUZ (O-RAN, TIP, Metaverse summit) happens the week after the O-RAN F-2-F (same place)
    3. 2022-09-27: Thoralf to create presentation material and send to subhash
  10. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-08-02
      1. hw-rust creation review by Johannes = https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70416 ?
      2. Sunil to contact Johannes that he abandons his change and we continue with Sunil's: https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70429
    2. 2022-09-13: working is progressing. end of September first commits should come.
    3. 2022-09-27: first commit likely coming this week. Johannes could demo in two weeks from now.
  11. RICAPP agenda: RICAPP Meetings.

2022-09-13 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. 2022-09-13 
      1. https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/9006 OK, (influx update) only deployment changes. So ok with test case.
      2. https://gerrit.o-ran-sc.org/r/c/ric-plt/stslgo/+/9010 OK, (influx update) test cases included.
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on 2022-05-27. 2022-08-30, 2022-09-13we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. 2022-09-13: one new bug: RIC-939
    2. RIC-939 race conditions in RMR → Abdulwahid
    3. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    4. RIC-915 dms_cli for installing xapp not working (raised by James)
    5. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    6. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    7. RIC-897 SCTP connection fails with Viavi // update with workaround
    8. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    9. RIC-894 long idle period (days) causes RMR connection breaks
    10. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    11. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    12. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    13. RIC-837 RMR is not forwarding messages from E2T to E2M
    14. RIC-835 → 2021-12-07 news from Viktor
    15. fixed: no new fixes.
    16. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
      2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
      3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
      4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
      5. 2022-04-26: still open
      6. 2022-05-11: expecting to finalize by May-27
      7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
      8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
      9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
      10. 2022-08-02: SUNIL SINGH to check any news on RIC-860 or RIC-878?
      11. 2022-08-16→2022-08-30->2022-09-13: no update
      12. : some cleanup is needed first.
        1. RIC-860 - suggestion is to merge the one abandoned RIC-860 review and the one that is still open into one review and keep that as new review.
        2. RIC-878 - suggest to re-start review 8500 and merge it with the current open one for RIC-878 and start this as new review.
        3. test both if they are actually working
        4. 2022-08-30: team currently busy, but will pick up on this again soon
      13. 2022-08-30: contributions by new contributor on asn.1 encoders/decoders and APER ASN.1↔XML tool - waiting for repo proposal
        1. 2022-09-13: Now hanging with Augu. - waiting for reply
  5. Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
    1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
    2. 2022-06-21
      1. RIC-642 (python) done
      2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
    3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-cpp) out of the F release. Which means they are likely early G release features.
    4. 2022-07-19: RIC-912 for clean up of the build process (should use dockerfile). But we first try to get current review through
    5. 2022-08-02: SUNIL SINGH check status with Anh Nguyen
    6. 2022-08-16: any news?
      1. one optinion is to cleanup CI first with the approach in RIC-912
      2. there are also instructions for testing CI given by LF infra. Thoralf-to dig out the instructions
    7. 2022-08-30  Waiting for Anh Nguyen to come fully back to work.
    8. 2022-09-13: now update, but Anh Nguyen is now back and in discussion with Anssi
  6. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: XTesting (used by Anuket) proposed as alternative to OTF (lack of support from OTF developers)
    5. 2022-07-19: James is working on it with LF
    6. 2022-08-02: any updates?
      1. caur.us (johannes@ c...) working on docker compose deployment (no K8S). usable in CI?
      2. James working Sridhar on xTesting.
    7. 2022-08-16 no news. Friday James will have further discussion with xTesting "evangelist" from Anuket
    8. 2022-08-30 progress on xTesting - first results to be presented in RSAC on Sep-21.
    9. 2022-09-13: kubectl version used in testing doesn't mahc expectations. Work in progress
  7. 2022-07-05: still one remaining demos.
    1. 10min RIC-642 xapp-frame-py subscription REST interface → end of August → (update 2022-08-16) middle of Sept (Erkki)
  8. G release content planning
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2022 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for G release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint G release dev sprint 1: Aug-22 to Sep-11
      2. Sprint G release dev sprint 2: Sep-12 to Oct-2
      3. Sprint G release dev sprint 3: Oct-3 to Oct-23
      4. Sprint G release dev sprint 4: Oct-24 to Nov-13 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-14 to Dec-4 (only for unplanned last-minute development items)
  9. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
    6. Thoralf to schedule a meeting once a proposal is ready.
    7. 2022-08-16 →2022-08-30 → 2022-09-13: no news yet, current approach we assume E2M manages E2 node to gNB list mapping and submgr (together with E2T) manage subscriptions. xApps to be aware of many E2T instances and many xApp instances.
  10. Meeting on E2 Reset scheduled for Apr-13->Apr-20 9:30am IST -> 2022-08-04
    1. 2022-08-30: Subhash presented the results of the discussion - material is here https://wiki.o-ran-sc.org/display/RICP/E2AP+2.0+Design 
  11. In O-RAN f-2-f in October, OSC has a three hour slot for presentations about what OSC did. RSAC coordinates this. Slideset on content of E and F release, show existing demo on RIC deploy, xapp deploy and connect simulator, show demo on E2AP2.0 incl. E2 config update (all together 30 min).
    1. 2022-09-13: likely the way we go forward - Subhash and Thoralf will handle
    2. FYI: FYUZ (O-RAN, TIP, Metaverse summit) happens the week after the O-RAN F-2-F (same place)
  12. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-08-02
      1. hw-rust creation review by Johannes = https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70416 ?
      2. Sunil to contact Johannes that he abandons his change and we continue with Sunil's: https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70429
    2. 2022-09-13: working is progressing. end of September first commits should come.
  13. 2022-09-13: Joseph Thaliath &  Sandeep J to present plans of OSC AI/ML subproject
    1. slideset: https://wiki.o-ran-sc.org/download/attachments/57377183/AIMLFW-KickOffMeeting.pdf?api=v2
  14. RICAPP agenda: RICAPP Meetings.

2022-08-30 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. 2022-08-30  We did not check this this time.
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on May-27-2022. 2022-08-30 we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. 2022-08-30: TODO
    2. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    3. RIC-915 dms_cli for installing xapp not working (raised by James)
    4. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    5. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    6. RIC-897 SCTP connection fails with Viavi // update with workaround
    7. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    8. RIC-894 long idle period (days) causes RMR connection breaks
    9. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    10. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    11. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    12. RIC-837 RMR is not forwarding messages from E2T to E2M
    13. RIC-835 → 2021-12-07 news from Viktor
    14. fixed: no new fixes.
    15. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
      2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
      3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
      4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
      5. 2022-04-26: still open
      6. 2022-05-11: expecting to finalize by May-27
      7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
      8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
      9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
      10. 2022-08-02: SUNIL SINGH to check any news on RIC-860 or RIC-878?
      11. 2022-08-16→2022-08-30: some cleanup is needed first.
        1. RIC-860 - suggestion is to merge the one abandoned RIC-860 review and the one that is still open into one review and keep that as new review.
        2. RIC-878 - suggest to re-start review 8500 and merge it with the current open one for RIC-878 and start this as new review.
        3. test both if they are actually working
        4. 2022-08-30: team currently busy, but will pick up on this again soon
      12. 2022-08-30: contributions by new contributor on asn.1 encoders/decoders and APER ASN.1↔XML tool - waiting for repo proposal
  5. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: XTesting (used by Anuket) proposed as alternative to OTF (lack of support from OTF developers)
    5. 2022-07-19: James is working on it with LF
    6. 2022-08-02: any updates?
      1. caur.us (johannes@ c...) working on docker compose deployment (no K8S). usable in CI?
      2. James working Sridhar on xTesting.
    7. 2022-08-16 no news. Friday James will have further discussion with xTesting "evangelist" from Anuket
    8. 2022-08-30 progress on xTesting - first results to be presented in RSAC on Sep-21.
  6. Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
    1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
    2. 2022-06-21
      1. RIC-642 (python) done
      2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
    3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-cpp) out of the F release. Which means they are likely early G release features.
    4. 2022-07-19: RIC-912 for clean up of the build process (should use dockerfile). But we first try to get current review through
    5. 2022-08-02: SUNIL SINGH check status with Anh Nguyen
    6. 2022-08-16: any news?
      1. one optinion is to cleanup CI first with the approach in RIC-912
      2. there are also instructions for testing CI given by LF infra. Thoralf-to dig out the instructions
    7. 2022-08-30  Waiting for Any Nguyen to come fully back to work.
  7. 2022-07-05: still one remaining demos.
    1. 10min RIC-642 xapp-frame-py subscription REST interface → end of August → (update 2022-08-16) middle of Sept (Erkki)
  8. G release content planning
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2022 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for G release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint G release dev sprint 1: Aug-22 to Sep-11
      2. Sprint G release dev sprint 2: Sep-12 to Oct-2
      3. Sprint G release dev sprint 3: Oct-3 to Oct-23
      4. Sprint G release dev sprint 4: Oct-24 to Nov-13 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-14 to Dec-4 (only for unplanned last-minute development items)
  9. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
    6. Thoralf to schedule a meeting once a proposal is ready.
    7. 2022-08-16 →2022-08-30 no news yet
  10. Meeting on E2 Reset scheduled for Apr-13->Apr-20 9:30am IST -> 2022-08-04
    1. 2022-04-26: in the meeting we discussed various ways how E2 reset can be implemented. We decided to check current specifications by O-RAN on how to support E2 Reset and how to align contributions with it.
    2. timer limitation still to be discussed and whether we can two implementations (with timer/without timer)
    3. Thoralf to schedule another meeting end of May (after F).
    4. 2022-06-07: Thoralf will schedule a meeting for week after next week
    5. 2022-06-21→2022-07-05: This has to wait for end of July
    6. 2022-08-02: meeting scheduled for 2022-08-04
    7. 2022-08-30: Subhash presented the results of the discussion - material is here https://wiki.o-ran-sc.org/display/RICP/E2AP+2.0+Design 
  11. In O-RAN f-2-f in October, OSC has a three hour slot for presentations about what OSC did. RSAC coordinates this. Slideset on content of E and F release, show existing demo on RIC deploy, xapp deploy and connect simulator, show demo on E2AP2.0 incl. E2 config update (all together 30 min).
  12. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-08-02
      1. hw-rust creation review by Johannes = https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70416 ?
      2. Sunil to contact Johannes that he abandons his change and we continue with Sunil's: https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70429
  13. RICAPP agenda: RICAPP Meetings.

2022-08-16 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. https://gerrit.o-ran-sc.org/r/c/ric-plt/ricdms/+/8824 → OK, as only new swagger yaml file for which nothing is implemented yet.
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on May-27-2022. 2022-08-16 we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. 2022-08-16: TODO
    2. RIC-936 change from gcr.ioghcr.io in master and f-release DONE
    3. RIC-935 flannel namespace change. fixed in master and f-release DONE
    4. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    5. RIC-915 dms_cli for installing xapp not working (raised by James)
    6. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    7. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    8. RIC-897 SCTP connection fails with Viavi // update with workaround
    9. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    10. RIC-894 long idle period (days) causes RMR connection breaks
    11. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    12. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    13. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    14. RIC-837 RMR is not forwarding messages from E2T to E2M
    15. RIC-835 → 2021-12-07 news from Viktor
    16. fixed: RIC-935, RIC-936
    17. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
      2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
      3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
      4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
      5. 2022-04-26: still open
      6. 2022-05-11: expecting to finalize by May-27
      7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
      8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
      9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
      10. 2022-08-02: SUNIL SINGH to check any news on RIC-860 or RIC-878?
      11. 2022-08-16: some cleanup is needed first.
        1. RIC-860 - suggestion is to merge the one abandoned RIC-860 review and the one that is still open into one review and keep that as new review.
        2. RIC-878 - suggest to re-start review 8500 and merge it with the current open one for RIC-878 and start this as new review.
        3. test both if they are actually working
  5. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: XTesting (used by Anuket) proposed as alternative to OTF (lack of support from OTF developers)
    5. 2022-07-19: James is working on it with LF
    6. 2022-08-02: any updates?
      1. caur.us (johannes@ c...) working on docker compose deployment (no K8S). usable in CI?
      2. James working Sridhar on xTesting.
    7. 2022-08-16 no news. Friday James will have further discussion with xTesting "evangelist" from Anuket
  6. Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
    1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
    2. 2022-06-21
      1. RIC-642 (python) done
      2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
    3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-cpp) out of the F release. Which means they are likely early G release features.
    4. 2022-07-19: RIC-912 for clean up of the build process (should use dockerfile). But we first try to get current review through
    5. 2022-08-02: SUNIL SINGH check status with Anh Nguyen
    6. 2022-08-16: any news?
      1. one optinion is to cleanup CI first with the approach in RIC-912
      2. there are also instructions for testing CI given by LF infra. Thoralf-to dig out the instructions
  7. 2022-07-05: still one remaining demos.
    1. 10min RIC-642 xapp-frame-py subscription REST interface → end of August → (update 2022-08-16) middle of Sept (Erkki)
  8. G release content planning
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2022 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for G release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint G release dev sprint 1: Aug-22 to Sep-11
      2. Sprint G release dev sprint 2: Sep-12 to Oct-2
      3. Sprint G release dev sprint 3: Oct-3 to Oct-23
      4. Sprint G release dev sprint 4: Oct-24 to Nov-13 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-14 to Dec-4 (only for unplanned last-minute development items)
  9. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
    6. Thoralf to schedule a meeting once a proposal is ready.
    7. 2022-08-16 no news yet
  10. Meeting on E2 Reset scheduled for Apr-13->Apr-20 9:30am IST -> 2022-08-04
    1. 2022-04-26: in the meeting we discussed various ways how E2 reset can be implemented. We decided to check current specifications by O-RAN on how to support E2 Reset and how to align contributions with it.
    2. timer limitation still to be discussed and whether we can two implementations (with timer/without timer)
    3. Thoralf to schedule another meeting end of May (after F).
    4. 2022-06-07: Thoralf will schedule a meeting for week after next week
    5. 2022-06-21→2022-07-05: This has to wait for end of July
    6. 2022-08-02: meeting scheduled for 2022-08-04
    7. 2022-08-16: Subhash to present results of discussion in next meeting on 2022-08-30
  11. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-08-02
      1. hw-rust creation review by Johannes = https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70416 ?
      2. Sunil to contact Johannes that he abandons his change and we continue with Sunil's: https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70429
    2. 2022-08-16: repo is now created ->Closed
  12. RICAPP agenda: RICAPP Meetings.

2022-08-02 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. 2022-08-02: no large commits
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on May-27-2022. 2022-08-02 we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. 2022-08-02: no new bugs, no new fixes
    2. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    3. RIC-915 dms_cli for installing xapp not working (raised by James) (2022-05-30 Thoralf added comment in the case)
    4. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    5. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    6. RIC-897 SCTP connection fails with Viavi // update with workaround
    7. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    8. RIC-894 long idle period (days) causes RMR connection breaks
    9. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    10. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    11. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    12. RIC-837 RMR is not forwarding messages from E2T to E2M
    13. RIC-835 → 2021-12-07 news from Viktor
    14. fixed:no new fixes
    15. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
      2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
      3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
      4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
      5. 2022-04-26: still open
      6. 2022-05-11: expecting to finalize by May-27
      7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
      8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
      9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
      10. 2022-08-02: SUNIL SINGH to check any news on RIC-860 or RIC-878?
  5. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: XTesting (used by Anuket) proposed as alternative to OTF (lack of support from OTF developers)
    5. 2022-07-19: James is working on it with LF
    6. 2022-08-02: any updates?
      1. caur.us (johannes@ c...) working on docker compose deployment (no K8S). usable in CI?
      2. James working Sridhar on xTesting.
  6. Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
    1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
    2. 2022-06-21
      1. RIC-642 (python) done
      2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
    3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-cpp) out of the F release. Which means they are likely early G release features.
    4. 2022-07-19: RIC-912 for clean up of the build process (should use dockerfile). But we first try to get current review through
    5. 2022-08-02: SUNIL SINGH check status with Anh Nguyen
  7. 2022-07-05: still one remaining demos.
    1. 10min RIC-642 xapp-frame-py subscription REST interface → end of August (Erkki)
  8. G release content planning
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2022 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for G release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint G release dev sprint 1: Aug-22 to Sep-11
      2. Sprint G release dev sprint 2: Sep-12 to Oct-2
      3. Sprint G release dev sprint 3: Oct-3 to Oct-23
      4. Sprint G release dev sprint 4: Oct-24 to Nov-13 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-14 to Dec-4 (only for unplanned last-minute development items)
  9. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
    6. Thoralf to scheduke a meeting once a proposal is ready.
  10. Meeting on E2 Reset scheduled for Apr-13->Apr-20 9:30am IST -> 2022-08-04
    1. 2022-04-26: in the meeting we discussed various ways how E2 reset can be implemented. We decided to check current specifications by O-RAN on how to support E2 Reset and how to align contributions with it.
    2. timer limitation still to be discussed and whether we can two implementations (with timer/without timer)
    3. Thoralf to schedule another meeting end of May (after F).
    4. 2022-06-07: Thoralf will schedule a meeting for week after next week
    5. 2022-06-21→2022-07-05: This has to wait for end of July
    6. 2022-08-02: meeting scheduled for 2022-08-04
  11. Pranesh raised the issue of message drops after idle times of about 15 minutes. Could be the same as RIC-894. May or not be related to K8S.
    1. 2022-07-19 no news
    2. 2022-08-02 → move to bug sections (Thoralf added this as comment to RIC-894)
  12. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-08-02
      1. hw-rust creation review by Johannes = https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70416 ?
      2. Sunil to contact Johannes that he abandons his change and we continue with Sunil's: https://gerrit.linuxfoundation.org/infra/c/releng/info-master/+/70429
  13. RICAPP agenda: RICAPP Meetings.

2022-07-19 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).2022-07-19:
        we did not do this this time
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on May-27-2022. 2022-07-19 we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. 2022-07-19: we did not check this this time.
    2. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    3. RIC-915 dms_cli for installing xapp not working (raised by James) (2022-05-30 Thoralf added comment in the case)
    4. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    5. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    6. RIC-897 SCTP connection fails with Viavi // update with workaround
    7. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    8. RIC-894 long idle period (days) causes RMR connection breaks
    9. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    10. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    11. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    12. RIC-837 RMR is not forwarding messages from E2T to E2M
    13. RIC-835 → 2021-12-07 news from Viktor
    14. fixed:no new fixes
    15. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
      2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
      3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
      4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
      5. 2022-04-26: still open
      6. 2022-05-11: expecting to finalize by May-27
      7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
      8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
      9. 2022-07-19: This is pending on LF to get permissions resolved and could then merge these.
  5. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: XTesting proposed as alternative to OTF
    5. 2022-07-19: James is workin on it with LF
  6. Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
    1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
    2. 2022-06-21
      1. RIC-642 (python) done
      2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
    3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-cpp) out of the F release. Which means they are likely early G release features.
    4. 2022-07-19: RIC-912 for clean up of the build process (should use dockerfile). But we first try to get current review through
  7. 2022-07-05: still two remaining demos.
    1.  2022-07-19: RIC-888 query interface in nodeb-rnib for querying RAN functions by OID. (Shobha)
      1. new function in https://gerrit.o-ran-sc.org/r/gitweb?p=ric-plt/nodeb-rnib.git;a=blob;f=reader/rNibReader.go -> GetRanFunctionDefinition()
      2. C version via creader (see https://packagecloud.io/o-ran-sc/release/packages/debian/stretch/rnib_1.2.5_all.deb)
      3. play video "RIC_888.mp4" from tmp folder (remember ... → "share sound")
    2. 10min RIC-642 xapp-frame-py subscription REST interface → end of August (Erkki)
    3. 2022-07-19: Thoralf uploaded demo on deploying RIC, connecting the simulator project's E2 (node) simulator, Nokia simulator and deploy the hw-go xapp as well: 2022-05-24 Release F
  8. F release wrap up
    1. 2022-07-05 & 2022-07-19: F release. See demo page: Release criteria checklist - Release F, Near-RT RIC (F release) = image list, F Release = summary, 2022-05-24 Release F = demos.
  9. G release content planning
    1. we mark items that you are >90% sure (=”committed”) to work on during 2H2022 with your label, like subteam-n (Nokia), subteam-s (Samsung) and so on. Items that are proposed for G release but not “committed” we mark with subteam-n-proposal, subteam-s-proposal and so on. To ease usage I created a couple of filters for follow up. See §7.3 from Jira usage conventions.
    2. Sprint dates
      1. Sprint G release dev sprint 1: Aug-22 to Sep-11
      2. Sprint G release dev sprint 2: Sep-12 to Oct-2
      3. Sprint G release dev sprint 3: Oct-3 to Oct-23
      4. Sprint G release dev sprint 4: Oct-24 to Nov-13 (last planned development sprint)
      5. Sprint G release dev sprint 5: Nov-14 to Dec-4 (only for unplanned last-minute development items)
  10. GRPC vs RMR
    1. Nokia is plannig RMR with GRPC (E2AP-equivalent xApp interfaces)
    2. to include Alexandre in discussion as well. Subhash also interested in what's coming. Nitin (mavenir) and Sunil (HCL) also interested.
    3. need to look at Mavenir E2SM-RC proposal.
    4. impact on xapp frameworks will happen as well.
    5. Alexandre mentioned option of using QUIC (grpc over QUIC).
  11. Meeting on E2 Reset scheduled for Apr-13->Apr-20 9:30am IST
    1. 2022-04-26: in the meeting we discussed various ways how E2 reset can be implemented. We decided to check current specifications by O-RAN on how to support E2 Reset and how to align contributions with it.
    2. timer limitation still to be discussed and whether we can two implementations (with timer/without timer)
    3. Thoralf to schedule another meeting end of May (after F).
    4. 2022-06-07: Thoralf will schedule a meeting for week after next week
    5. 2022-06-21→2022-07-05: This has to wait for end of July
  12. Pranesh raised the issue of message drops after idle times of about 15 minutes. Could be the same as RIC-894. May or not be related to K8S.
    1. 2022-07-19 no news
  13. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-07-19 TOC approved ric-plt/xapp-frame-rust is ready for content. ric-app/hw-rust still to be created
    2. 2022-07-19 go through commit steps
  14. RICAPP agenda: RICAPP Meetings.

2022-07-05 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).2022-07-05:
        we did not do this this time
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on May-27-2022. 2022-07-05 we did not do this this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. 2022-07-05: we did not check this this time.
    2. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    3. RIC-915 dms_cli for installing xapp not working (raised by James) (2022-05-30 Thoralf added comment in the case)
    4. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    5. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    6. RIC-897 SCTP connection fails with Viavi // update with workaround
    7. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    8. RIC-894 long idle period (days) causes RMR connection breaks
    9. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    10. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    11. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    12. RIC-837 RMR is not forwarding messages from E2T to E2M
    13. RIC-835 → 2021-12-07 news from Viktor
    14. fixed:no new fixes
    15. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. Sangeetha working on RIC-860, done, but code still to be checked in. 2022-07-05& 2022-07-19 update:  - Code checked-in, but it seems https://gerrit.o-ran-sc.org/r/c/it/test/+/8530 that is part of GIT relation chain was abandoned (it contained the bulk of the changes for subscription deletion test)
      2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 2022-07-05 & 2022-07-19 update:  - Code checked-in
      3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
      4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
      5. 2022-04-26: still open
      6. 2022-05-11: expecting to finalize by May-27
      7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
      8. 2022-07-05: Thoralf marked RIC-860 and RIC-878 as moved out of F release
  5. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: Xtesting proposed as alternative to OTF
    5. 2022-07-05: Any news from James?
  6. Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
    1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
    2. 2022-06-21
      1. RIC-642 (python) done
      2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
    3. 2022-07-05: Thoralf moved RIC-705 and RIC-641 (xapp-frame-py) out of the F release. Which means they are likely early G release features.
  7. 2022-07-05: still two remaining demos.
    1. No demo today (plan for 2022-07-19) 5 min RIC-888 query interface in nodeb-rnib for querying RAN functions by OID. (Manoj)
    2. 10min RIC-642 xapp-frame-py subscription REST interface → end of August (Erkki)
    3. 2022-07-05: Thoralf uploaded demo on deploying RIC, connecting the simulator project's E2 (node) simulator, Nokia simulator and deploy the hw-go xapp as well: 2022-05-24 Release F
  8. F release wrap up
    1. 2022-07-05 & 2022-07-19: F release. See demo page: Release criteria checklist - Release F, Near-RT RIC (F release) = image list, F Release = summary, 2022-05-24 Release F = demos.
  9. Meeting on E2 Reset scheduled for Apr-13->Apr-20 9:30am IST
    1. 2022-04-26:
      1. in the meeting we discussed various ways how E2 reset can be implemented. We decided to check current specifications by O-RAN on how to support E2 Reset and how to align contributions with it.
      2. timer limitation still to be discussed and whether we can two implementations (with timer/without timer)
      3. Thoralf to schedule another meeting end of May (after F).
      4. 2022-06-07: Thoralf will schedule a meeting for week after next week
    2. 2022-06-21→2022-07-05: This has to wait for end of July
  10. Pranesh raised the issue of message drops after idle times of about 15 minutes. Could be the same as RIC-894. May or not be related to K8S.
    1. 2022-07-05 no news
  11. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-06-21: We had a meeting on this last week and proposal for TOC is in the making. Two new components: ric-plt/xapp-frame-rust and ric-app/hw-rust)
    2. 2022-07-05:
      1. addition of ric-plt/xapp-frame-rust and ric-app/hw-rust was approved by TOC on Jun-23-2022.
      2. Thoralf to create the repos once back from holiday (mid July)
  12. RICAPP agenda: RICAPP Meetings.


2022-06-21 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/8368 OK cleanup of ric-dep and it-dep (only copied code)
    2. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493 OK
    3. https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-py/+/8569 OK
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this last on May-27-2022. Not done this time
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-921 fix UT test case in e2mgr to stub time (leftover from review https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8493)
    2. RIC-915 dms_cli for installing xapp not working (raised by James) (2022-05-30 Thoralf added comment in the case)
    3. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    4. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    5. RIC-897 SCTP connection fails with Viavi // update with workaround
    6. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    7. RIC-894 long idle period (days) causes RMR connection breaks
    8. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    9. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    10. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    11. RIC-837 RMR is not forwarding messages from E2T to E2M
    12. RIC-835 → 2021-12-07 news from Viktor
    13. fixed: RIC-920 (gNB ID fix)
    14. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. Sangeetha working on RIC-860, done, but code still to be checked in.  
      2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in. 
      3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
      4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
      5. 2022-04-26: still open
      6. 2022-05-11: expecting to finalize by May-27
      7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
  5. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
    4. 2022-06-21: Xtesting proposed as alternative to OTF
  6.  Progress on xapp side adaptation to REST interface? RIC-641 Sandeep→ Anh Nguyen (HCL) is working on this. Work is progressing.
    1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
    2. 2022-06-21
      1. RIC-642 (python) done
      2. RIC-705 and RIC-641 being worked on by Anh Nguyen: https://gerrit.o-ran-sc.org/r/c/ric-plt/xapp-frame-cpp/+/8561
  7. 2022-06-21: demo held on 2022-07-06. Remaining demos planned for 2022-06-21
    1. No demo today (plan for 2022-07-19) 5 min RIC-888 query interface in nodeb-rnib for querying RAN functions by OID. (Manoj)
    2. 10min RIC-916 new reconnect timer in E2 to reject new connect for x seconds (dhiraj)
    3. 10min RIC-642 xapp-frame-py subscription REST interface → end of August (Erkki)
  8. F release wrap up
    1. see §6 in Jira usage conventions
    2. Thoralf to go through JIRA and check status of items. Thoralf might send e-mails to get current status.
    3. Thoralf to organize sprint demos for May-24, at 9am ET in an extended timeslot of the project meeting.
      1. See demo page: 2022-05-24 Release F
  9. New contribution proposals: Thoralf created JIRA items for the items in c and d and b: Link =https://jira.o-ran-sc.org/issues/?jql=labels%20%3D%20subteam-p
    1. Meeting on E2 Reset scheduled for Apr-13->Apr-20 9:30am IST
      1. 2022-04-26:
        1. in the meeting we discussed various ways how E2 reset can be implemented. We decided to check current specifications by O-RAN on how to support E2 Reset and how to align contributions with it.
        2. timer limitation still to be discussed and whether we can two implementations (with timer/without timer)
        3. Thoralf to schedule another meeting end of May (after F).
        4. 2022-06-07: Thoralf will schedule a meeting for week after next week
        5. 2022-06-21: This has to wait for end of July
  10. Pranesh raised the issue of message drops after idle times of about 15 minutes. Could be the same as RIC-894. May or not be related to K8S.
  11. RUST as a language for xApps and framework. Will take this in the details in next meeting.
    1. 2022-06-21: We had a meeting on this last week and proposal for TOC is in the making. Two new components: ric-plt/xapp-frame-rust and ric-app/hw-rust)
    2. Approved by the TOC.
  12. RICAPP agenda: RICAPP Meetings.

2022-06-07 (Tuesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. https://gerrit.o-ran-sc.org/r/c/ric-plt/nodeb-rnib/+/8324  OK (commit of previously reviewed files in e2ap branch)
    2. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8303 OK (commit of previously reviewed files in e2ap branch)
    3. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2/+/8323 OK (commit of previously reviewed files in e2ap branch)
    4. https://gerrit.o-ran-sc.org/r/c/ric-plt/nodeb-rnib/+/8332 OK (change in proto file that caused changes in generated files)
    5. https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/8368 OK (lots of code moved from it/dep repo)
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. Thoralf did this on May-27-2022 - no surprises
    4. ric-plt/alarm-go 0,0 // no bugs (2021-11-22 → 2022-02-13 → 2022-05-26)
    5. ric-plt/appmgr 19,3 // 1 major bug (2022-01-30 → 2022-02-13 → 2022-05-26)
    6. ric-plt/e2mgr 88,6 → 87,7 // no bugs (2021-11-18 → 2022-02-14 → 2022-05-27)
    7. ric-plt/lib/rmr 86,1 // no bugs (2021-11-23 → 2022-02-08 → 2022-05-24)
    8. ric-plt/sdlgo 90,2 → 90,5 // no bugs (2022-01-31 → 2022-02-14 → 2022-05-27)
    9. ric-plt/submgr 51,4 // no bugs (2022-01-30 → 2022-02-13 → 2022-05-27)
    10. ric-plt/tracelibcpp 0,0 // 1 major bug (2022-01-25 → 2022-02-08 → 2022-05-24)
    11. ric-plt/tracelibgo 96,2 //0 bugs (2022-01-30 → 2022-02-13 → 2022-05-27)
    12. ric-plt/xapp-frame 0,0 // no bugs (2021-11-22 → 2022-02-13 → 2022-05-26)
    13. ric-plt/xapp-frame-cpp 95,6 → 96,3 // no blocker bugs (2022-01-26 → 2022-02-00 → 2022-05-25)
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-915 dms_cli for installing xapp not working (raised by James) (2022-05-30 Thoralf added comment in the case)
    2. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    3. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    4. RIC-897 SCTP connection fails with Viavi // update with workaround
    5. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    6. RIC-894 long idle period (days) causes RMR connection breaks
    7. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    8. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    9. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    10. RIC-837 RMR is not forwarding messages from E2T to E2M
    11. RIC-835 → 2021-12-07 news from Viktor
    12. fixed: no new fixes
    13. anybody would like to get more familiar with RMR?
  4. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. Sangeetha working on RIC-860, done, but code still to be checked in.
      2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in.
      3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
      4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
      5. 2022-04-26: still open
      6. 2022-05-11: expecting to finalize by May-27
      7. 2022-06-07: news on RIC-860 and RIC-878 or O1 testing?
  5. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
        1. 2022-05-30: Thoralf comment in RIC-915
  6. Progress on E2APv2.0?
    1. in xapps? E2APv2.0 update in xApps that use the old RMR to-be-removed xapp subscription interface - Thoralf asking Sunil to coordinate xapp-side adaptation to REST interface - see RIC-375
      1. kpimon
      2. bouncer (working on rest based submgr API if that means HCL is working RIC-641, please inform Alexandre about this.
      3. all hello-world xapps (hw-go already uses submgr REST ifc)
        1. hw-go issue with old xapp frame lib used. - needs to be updated.
      4. update simulators (discuss with Subhash if needed) do we have two simulators we have to update?
        1. done, but not yet open for review.
        2. 2022-05-30: Simulator worked fine, but thoralf raised SIM-99 for supporting source-address binding in the simulator
      5. 2022-05-31: as we're not ready with RIC-641 (cpp) and RIC-642 (python) we decided to still keep RMR enabled as interface provided by the subscription manager. RIC-642 is almost ready, and I understand RIC-641 is also being worked on.  07-06-2022 - RIC-641 HCL team is working on this.   
      6. 07-06-2022: E2APv2.0 - Code merged
    2. in DU
      1. 2022-02-23 user-30c9d reported in TOC that this work is done.
  7. RIC-641 Sandeep (HCL) is working on this. Work is progressing.
    1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
    2. 2022-04-26: working on it
    3. 2022-05-11: news? Could be handled as exception to be worked on during May-15 to Jun-5 so we can still include this into F.
    4. 2022-06-07: Any news?
  8. F release wrap up
    1. see §6 in Jira usage conventions
    2. Thoralf to go through JIRA and check status of items. Thoralf might send e-mails to get current status.
    3. Thoralf to organize sprint demos for May-24, at 9am ET in an extended timeslot of the project meeting.
      1. See demo page: 2022-05-24 Release F
      2. 2022-07-06 demo held. Remaining demos planned for 2022-06-21
        1. 5 min RIC-888 query interface in nodeb-rnib for querying RAN functions by OID. (Manoj)
        2. 10min RIC-916 new reconnect timer in E2 to reject new connect for x seconds
  9. New contribution proposals: Thoralf created JIRA items for the items in c and d and b: Link =https://jira.o-ran-sc.org/issues/?jql=labels%20%3D%20subteam-p
    1. Meeting on E2 Reset scheduled for Apr-13->Apr-20 9:30am IST
      1. 2022-04-26:
        1. in the meeting we discussed various ways how E2 reset can be implemented. We decided to check current specifications by O-RAN on how to support E2 Reset and how to align contributions with it.
        2. timer limitation still to be discussed and whether we can two implementations (with timer/without timer)
        3. Thoralf to schedule another meeting end of May (after F).
        4. 2022-06-07: Thoralf will schedule a meeting for week after next week
  10. Pranesh raised the issue of message drops after idle times of about 15 minutes. Could be the same as RIC-894. May or not be related to K8S.
  11. Note - 6-7-2022 : Matti send a mail on this.  RUST as a language for xApps and framework. Will take this in the details in next meeting.
  12. RICAPP agenda: RICAPP Meetings.

2022-05-24

we used this slot as demo meeting for the F release. Demo recording: 2022-05-24 Release F

2022-05-11 (exceptionally Wednesday)

Recording: link to zoom recording

  1. Every time: Check rule RC-4 (link) that all L or XL commits of the last two weeks have also new unit tests. This is our policy. link-to-reviews (gerrit filter instructions // gerrit t-shirt-sizing).
    1. https://gerrit.o-ran-sc.org/r/c/ric-plt/a1/+/8127 ok
    2. https://gerrit.o-ran-sc.org/r/c/ric-plt/stslgo/+/8112 ok
    3. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8136 ok
    4. https://gerrit.o-ran-sc.org/r/c/ric-plt/ric-dep/+/8147 ok - as only files only moved from other repo
    5. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8196 ok
    6. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8215 ok
    7. https://gerrit.o-ran-sc.org/r/c/ric-plt/e2mgr/+/8218 ok
    8. https://gerrit.o-ran-sc.org/r/c/ric-plt/submgr/+/7592 ok
  2. every second time: Review code coverage stats and blocker code smells
    1. We take a look at the two links in the beginning of this page: Code coverage reports..
    2. The list below is only working reports // Anybody volunteering to work with LF on making the code coverage CI to work again (there's still the old JVM version)
    3. We did not do this today.
  3. Every time: Check if there are new bug reports in JIRA: link
    1. RIC-905 new (from PW) Issue in reporting the CLEAR ALARM as VES EVENT
    2. RIC-903 new (from PW) DefaultUser setup fails when authentication is enabled for InfluxDB. 2022-05-11: fixed
    3. RIC-901 new (from PW) BUG FIX IN 'Get ALARM INFO’ NETCONF COMMAND
    4. RIC-897 SCTP connection fails with Viavi // update with workaround
    5. RIC-896 xapps sending same msg type and sub id fails - details to be clarified
    6. RIC-894 long idle period (days) causes RMR connection breaks
    7. RIC-890, RIC-891, RIC-892: build of xapp-ccp framework seems to fail. 2022-05-11: fixed
      1. could be staging repo related (10004) vs release repo (10002) for the base image
    8. RIC-864 xapp-frame-cpp CI does not use Dockerfile and therefore uses Ubuntu18.04 (not 20.04) in build
    9. RIC-857 sporadically RMR takes multiple minutes before being "ready"
    10. RIC-852 Intermittent Issue with E2T: While setting up E2 setup request and response.
      1. 2021-12-21: Trying to get bandwidth for this during F release.
    11. RIC-837 RMR is not forwarding messages from E2T to E2M
    12. RIC-835 → 2021-12-07 news from Viktor
    13. fixed: RIC-903, RIC-890, RIC-891, RIC-892
    14. anybody would like to get more familiar with RMR?
  4. 2022-06-07: We plan to release in June. Thoralf will coordinate creation of container images by e-mail.
    1. F release tasks for releasing the container images: Near-RT RIC (F release)
    2. F release status: F Release
    3. F release criteria checklist (filled in by Thoralf): Release criteria checklist - Release F
  5. Sunil still to discuss with other team members for other items from subteam-h
    1. Other tickets CI/CD and Code coverage tickets? Sunil: I am still looking for the resources to work on that.
      1. Sangeetha working on RIC-860, done, but code still to be checked in.
      2. Sangeetha working on RIC-878, status see Jira item, code still to be checked in.
      3. O1 testing is also being worked on. 2022-03-29 Sangeetha to raise Jira ticket
      4. Subhash asked for documentation of nanobot from Sunil. Almost done. 2022-05-11: Still open
      5. 2022-04-26: still open
      6. 2022-05-11: expecting to finalize by May-27
  6. James: RSAC recommended incorporating OTF in testing (David Kinsey can help)- Thoralf to start mail thread with HCL (sunil, Sangeetha) and David on this plus James.
    1. 2022-04-12
      1. last Thursday RSAC call was used for preparing OTF installation of the three microservices into O-Cloud (WR k8s with O2 IMS/DMS) to avoid firewall issues
      2. actual workshop planned for RSAC on Apr-21 9am EDT.
      3. Taking OTF into use in E release might be only partially done in E release (also discussed in last week's TOC)
    2. 2022-04-26
      1. OTF installed and configured in Bedminster lab. Still access issues, though. Workshop planned for next Wed morning, 8am ET.
      2. David K. shared a lab network picture with the RIC on a separate network. Thoralf not sure why. Subhash and Thoralf interested in the document shared in last RSAC meeting.
    3. 2022-05-11:
      1. Currently in the hands of OTF team (Alex)
      2. dms_cli seems to have issues (James has used this in E release), dms_cli does not have CI/CD case. For now, let's agree if a good problem report is sent, Nune or Thoralf can look at it.
  7. Progress on E2APv2.0?
    1. in ric platform and simulators?
      1. 2022-04-26
        1. subscription manager change for E2APv2.0 is now in E2APv2.0 branch
        2. config update message support coming this week.
        3. after this cleanup of small things here and there that are still needed.
      2. 2022-05-10
        1. thoralf suggests May-13 as day for moving E2AP branch to master
          1. Subhash agrees. So let's aim for that.
          2. Subhash to list which Config transfer failure cases move into next release (just left-over create JIRA item)
        2. Nokia has already tested some E2APv2.0 procedures with Nokia simulator (like E2 setup, subscription success case)
        3. Subhash still working on simulator in sim project
    2. in xapps? E2APv2.0 update in xApps that use the old RMR to-be-removed xapp subscription interface - Thoralf asking Sunil to coordinate xapp-side adaptation to REST interface - see RIC-375
      1. kpimon
      2. bouncer (working on rest based submgr API if that means HCL is working RIC-641, please inform Alexandre about this.
      3. all hello-world xapps (hw-go already uses submgr REST ifc)
        1. hw-go issue with old xapp frame lib used. - needs to be updated.
      4. update simulators (discuss with Subhash if needed) do we have two simulators we have to update?
        1. done, but not yet open for review.
    3. in DU
      1. 2022-02-23 user-30c9d reported in TOC that this work is done.
  8. RIC-641 Sandeep (HCL) is working on this. Work is progressing.
    1. 2022-04-12: framework changes done. Now integrating with Bouncer xApp. The reviews are coming.
    2. 2022-04-26: working on it
    3. 2022-05-11: news? Could be handled as exception to be worked on during May-15 to Jun-5 so we can still include this into F.
  9. F release wrap up
    1. see §6 in Jira usage conventions
    2. Thoralf to go through JIRA and check status of items. Thoralf might send e-mails to get current status.
    3. Thoralf to organize sprint demos for May-24, at 9am ET in an extended timeslot of the project meeting.
      1. See demo page: 2022-05-24 Release F
  10. New contribution proposals: Thoralf created JIRA items for the items in c and d and b: Link =https://jira.o-ran-sc.org/issues/?jql=labels%20%3D%20subteam-p
    1. Meeting on E2 Reset scheduled for Apr-13->Apr-20 9:30am IST
      1. 2022-04-26:
        1. in the meeting we discussed various ways how E2 reset can be implemented. We decided to check current specifications by O-RAN on how to support E2 Reset and how to align contributions with it.
        2. timer limitation still to be discussed and whether we can two implementations (with timer/without timer)
        3. Thoralf to schedule another meeting end of May (after F).
  11. Pranesh raised the issue of message drops after idle times of about 15 minutes. Could be the same as RIC-894. May or not be related to K8S.
  12. RICAPP agenda: RICAPP Meetings.

2022-04-26

Recording: link to zoom recording

...